The ITmk3 proces s, which produces high-quality iron

(ITmk3 iron nuggets) from ore fines and coal fines, was

developed bas ed on a unique concept of iron ore and

carbon composite technology. The development started

in 1996, followed by test operations at a pilot plant and

large-scale pilot plant. The first commercial plant was

constructed in the U.S. and has started producing iron

nugget

s . Thi

s

article outline

s

the hi

s

tory of the

development, the features of the proces s, the product, and the future outlook.

Introduction

ITmk3 (pronounced as "[ai ti:] mark three") is a rapid ironmaking process that includes reducing ore, carburizing & melting iron and separating slag, all at relatively low temperatures.

Referring to generation classes of ironmaking processes, the first generation would be the blast furnace (BF) process, which is the current mainstream. The second is the direct reduction ironmaking (DRI) process as typified by the MIDREX process. ITmk3 (Ironmaking Technology Mark 3) falls in the third generation category; it is a process based on a concept totally different from those of the earlier generations. In the ITmk3 process, a series of reactions occur within about 10 minutes. The reactions occur much faster in this process than in BF and DRI processes. In a typical BF process, raw materials dwell in a furnace for about 8 hours, while in the MIDREX process, the materials stay in a shaft furnace for 6 hours.

1. Developmental backgrou nd

Blast furnace processes require pretreatments such as producing coke from coking coal and preparing sinter from iron ore. Thus, an integrated steel mill with a blast furnace must have a capacity greater than 10,000 tonnes/day to be feasible. This limits the types of resources, such as raw materials, that can be used. The production may also lack in flexibility. Direct reduction ironmaking processes using natural gas, on the other hand, are limited as to plant locations. DRI plants can be built only in areas where natural gas is produced at a low cost.

Thus, the industry has focused on new processes that utilize the abundant reserves of fine ore and fuel coal. In the 1980s, various attempts were made to dev elop a new process, including the smelting reduction process. With this background, Kobe Steel and its US subsidary, MIDREX Technologies, Inc., developed a process called FASTMET, which produces reduced iron by heating agglomerates consisting of fine ore and coal.

In 1995, when developing the FASTMET process, the companies found that metallic iron can be separated from slag within ten minutes of heating. This reaction principle was adapted for a new ironmaking process, ITmk3. This paper describes the details of the new process.

Fig. 1is the iron-carbon phase diagram, which compares the operational regions of ironmaking processes, including ITmk3. The blast furnace (BF) process produces pig-iron saturated with carbon at a temperature around 1,500 , while ITmk3 produces metallic iron with higher purity at a temperature lower than that required for BF.

2. Basic research

Kobe Steel began to study a new ironmaking process in 1996. Using a tube furnace installed at the Iron & Steel Research Center (Kakogawa Works, Kobe Steel), the company found that metallic iron grows rapidly, being separated from slag, at a relatively low temperature. Fig. 2shows this phenomenon occurring in the tube furnace. After this result was reported and became the subject of repeated discussions among researchers, domestic and overseas, the conclusion was reached that this was an unprecedented phenomenon. The new ironmaking process was called ITmk3.

The company initiated collaborative research involving universities and institutes, domestic and overseas, and installed a box-type furnace at the Iron & Steel Research Center to conduct experiments on a larger scale. Fig. 3 shows hot samples discharged from the box furnace. Metallic iron has a bright orange color, while slag appears in dark orange, showing they are clearly separated from each other. Tohoku Univ ersity and Tokyo Institute of Technology conducted research to elucidate the reaction mechanism of this new ironmaking phenomenon 1), 2). University of Surrey, in the UK, conducted research on heating methods, using a large multi-stage box furnace newly installed at their site (Fig. 4). Max Planck Institute in Germany studied the equation modeling of the reactions 3).

The reaction between iron ore and coal remains the same as that for general ironmaking and is expressed as follows:

Fe x O y + yCO = xFe + yCO 2

(1) CO 2 + C = 2CO

(2) C(s) C (carburized) (3) Fe(s) Fe(l) (melt) (4) Reactions (1) and (2) occur in the FASTMET process. In the ITmk3 process, there are the additional reactions (3) and (4), which separate metallic iron from slag.

In this new ironmaking process, particles of iron ore and coal exist next to each other in each agglomerate. This is in contrast with the BF and DRI processes, which use bulky materials such as iron ore and coke, and may explain the fast reaction of the new process to some extent. However, this does not fully explain the rapidity of the reactions. Another series of experiments, conducted at the Kobe Steel Iron & Steel Research Center, confirmed a similar phenomenon. In these experiments, typical ores and coals, four types each, were combined and were heated in a box furnace. A study was conducted to clarify the effect of raw materials, temperature and furnace atmosphere on the reactions. Another study was conducted to elucidate the reaction mechanism. This study involved investigating the cross sections of agglomerates in the stages of reducing, melting and slag-separating, respectively. Fig. 5 shows sample results of the cross-sectional study. During the first three minutes, the agglomerate, consisting of fine ore and coal, did not exhibit any significant change in appearance, despite the reduction reaction that should have occurred inside. After five minutes, the metallic iron and slag started to partially melt and became separated. In about six minutes, the entire agglomerate started to melt rapidly, with metallic iron being separated from the slag. After

nine

minutes, they had separated completely. University of Surrey conducted experiments to optimize this process reaction by separately controlling the reduction and melting. Separable control is a feature of their multi-stage box furnace.

In the reaction mechanism, the rapid carburizing phenomenon could not be explained by the conventional theories of gas carburization or solid carburization. Much time was devoted to elucidating the new carburizing phenomenon. Unlike the shaft furnaces used for DRI plants, the contribution of gas carburization is considered to be small. A recent study by Tohoku University found carburization via liquid slag2), which appears to contribute to the rapid carburization along with solid carburization.

Using the box furnace at the Iron & Steel Research Center, Kobe Steel tested over a hundred types of raw materials, which verified the versatility of the raw materials that can be used for the ITmk3 process. The tests included applicability tests on low grade materials, such as iron ore containing a large amount of crystal water, oil coke and upgraded brown coal (UBC). They confirmed the applicability of these low grade materials.

3. Application of new ironmaking method

3.1 Pilot plant

In parallel with the basic research, application

studies were conducted on the new ironmaking process based on this unique carburization phenomenon.Among the various

processes deliberated, granular ironmaking was chosen as the most feasible approach. Designing of a pilot plant began in 1998. Unlike box furnaces, in which reactions occur under ideal conditions, the pilot plant had many issues to be addressed. Process development was conducted to resolve these issues.

Fig. 6shows the process flow of granular ironmaking. The process comprises

1) agglomerating iron-ore and coal (blue),

2) reducing and melting the agglomerates (red),

3) separating metallic iron from slag (green), and

4) treating exhaust and recovering heat (yellow).

The pilot plant employs a rotary hearth furnace, which facilitates radiation heating, to exploit the rapid reaction feature of ITmk3. In a smelting reduction process, melting occurs before reduction, during which FeO may corrode furnace refractory. To avoid this, reduction and smelting technology was adopted in which melting occurs after reduction is completed.

In a rotary hearth furnace (RHF), the heating combustion gas from a burner may adversely affect the reductive atmosphere in the furnace. To resolve this issue, the Mechanical Research Laboratory at Kobe Steel conducted a simulation study based on the computational fluid dynamics (CFD) to optimize the RHF, in the designing stage, for gas characteristics such as temperature distribution and flow (Fig. 7).

There are many technical challenges in continuously producing metallic iron by melting raw materials on the hearth of a furnace. Once melted and separated from slag, the metallic iron is cooled, solidified and discharged out of the furnace. This subjects the furnace hearth to repetitive thermal stress in short cycles. The furnace hearth must also resist corrosion caused by the slag

reacting on the hearth. Several tens of types of refractories were tested in order to identify the one best suited for the purpose. Repetitive thermal stress, involving rapid heating and cooling, was applied using an experimental furnace owned by a refractory manufacturer. A box furnace was used to clarify the corrosion behavior of slag. The hearth refractory was determined based on these experiments.

Although important, the selection of the hearth refractory does not resolve all the issues associated with the continuous production of granular iron. The key to the process is to maintain the hearth in good condition during the entire process, including the charging and discharging of materials to/from the furnace. Studies using the box furnace made such a technology available for the pilot plant.

A major difficulty was to design an apparatus for retrieving granular iron from an RHF. Although cooled and solidified, the granular iron is still at an elevated temperature. Several methods were contemplated. Having expertise in equipment for handling hot iron, specialists at Kobe Steel's Machinery and Engineering Company (currently, Machinary Business) designed the discharging apparatus. The Materials Research Laboratory of Kobe Steel collaborated in the selection of materials used for the apparatus.

In June 1999, within one year of the beginning of process development and designing, Kobe Steel started the construction of a small pilot plant, with a capacity of 3,000 tonnes/year, at its Kakogawa Works (Fig. 8). Experimental operation began at the end of August 1999. In September, the operation began to produce reduced iron. The plant was confirmed as producing iron reduced over 90% as originally planned. Then, the operating temperature was raised to successfully produce granular iron for the first time. In the beginning, operation continued for about six hours a day, during which various adjustments were made to the raw material mixture, heat pattern, furnace atmosphere and retention time. Improvements were also pursued for productivity and the quality of the granular iron. During these continuous operations, each lasting for about six hours, there were no problems with the hearth -a major concern -nor was there any significant mechanical failure. Experiments continued at a good pace (Fig. 9).

In late November, when the company started continuous operations lasting for an extended period of time, a pool of molten iron began to form on the hearth and grew larger and larger. It was not possible to cool and solidify this large pool of molten iron, a problem that necessitated the development of a new technology.

In April 2000, a new technology for maintaining the hearth was developed through observing the changes that occur on the hearth, completing the first campaign of the pilot plant.

The second campaign operation began in the latter part of 2000 with a view to receiving visits from potential collaboration partners and operating for an extended period of time.

This campaign succeeded in conducting a stable operation that continued for the target number of days, the result of a modified hearth maintenance technology. The hearth was repaired periodically while producing granular iron, which enabled continuous operation. This approach has no theoretical limits on continuity and advanced the

application. During the campaign, data were collected for the design and operation of a large pilot plant that followed.

While conducting this experimental operation, Kobe Steel was visited by potential partners, who were given tours of the site. Among the visitors, the most interested were those in the consortium organized by Iron Range Resources, Cleveland-Cliffs Inc. (currently, Cliffs Natural Resources), the largest mining company in North America, and Steel Dynamics, Inc., the second largest EAF based steel manufacturer. Iron Range Resources and Cleveland-Cliffs Inc. had attempted to revitalize

the mining industry, while Steel Dynamics, Inc. had been searching for a stable supply of iron source. Their aims coinciding, they were in search of a partner for collaborative development.

In March 2002, the decision was made to construct a large pilot plant in the beneficiation and pelletizing facility of Northshore Mining, Minnesota, owned by Cleveland-Cliffs. Different roles were allotted for the collaboration: Kobe Steel to provide technology and to design the pilot plant, Cleveland-Cliffs to supply iron ore and to provide operators, Steel Dynamics to receive and evaluate the product granular iron, and Iron Range Resources to finance the project. Later, the U.S. Department of Energy also provided financing, recognizing the project as the development of a new ironmaking technology with excellent energy efficiency.

3.2 Large pilot plant

In 2002, designing began for the large pilot plant. MIDREX Technologies, Inc. collaborated in designing the details. An RHF was the heart of the pilot plant. There were many rotary hearth furnaces for heating, with sizes up to 50m (diameter) 7m (hearth width), delivered to the market. A goal was set for the first commercial plant to have a size close to that described above (50m 7m). This would make the target capacity of the commercial plant about 500 thousand tonnes/year, judging from the productivity achieved by the small pilot plant.

The larger the pilot plant, the smaller the risk in upsizing it to a commercial scale; however, developing a large pilot plant may become too costly. Therefore, care must be taken in deciding the size of the pilot plant.

The following describes two factors emphasized in determining the size of the rotary hearth furnace used for the large pilot plant.

1) In the ITmk3 process, the secondary combustion

of the carbon monoxide generated i n carbon

composite agglomerates significantly affects

energy efficiency and the reductive atmosphere

in the furnace. The energy input (furnace gas

volume) for producing a tonne of granular iron

was correlated to the production amount

(Fig.10). The capacity of the large pilot plant

was determined to be 25,000 tonnes/year,

which is at the folding point of the correlation

curve.

2) The key to this process is the maintenance

technology for the furnace hearth, and the

h earth width is an important factor. Considering

the hearth width of 7m for the commercial

plant, a conservative scale-up factor, from the

pilot to commercial, was considered to be a

factor of 3 or 4. Assuming a similar scale-up

factor for the small pilot plant in Kakogawa, the

hearth width for the large pilot plant was

determined to be 2m.

The furnace profile was determined using the CFD model, which was further optimized

by feedback data from the operation of the

small pilot plant.

As it involves the development of a process, the project must minimize the risk to equipment. Because of this, the large pilot plant had to adopt industrially proven equipment as much as possible. Another prerequisite was that the equipment could be used for the commercial plant. In the end, the only apparatuses especially designed for this process were the charging and discharging units for the RHF. The rest were chosen from among those that had been industrially proven.

The process flow for the large pilot plant is basically the same as that for the small pilot plant, except that, for separating iron from slag, the small pilot plant adopts a batch-type process, while the large pilot plant adopts a continuous process.

The construction of the large pilot plant began in June 2002. The plant was completed and blown-in in May 2003. The first day was spent in producing reduced iron with a high metallic ratio, as in the

case of the small pilot plant. The production of granular iron succeeded on the second day. The large-scale demonstration followed and continued for 15 months until August 2004 (Fig. 11).

The following four campaigns were conducted during the demonstration operation:

1) optimizing the hearth maintenance technology

2) improving productivity and granular iron

quality

3) improving the unit consumption of fuel

(optimizing the secondary combustion)

4) testing performance

Various improvements were made during these campaigns. The demonstration by the prototype

plant went smoothly for an extended period of time with an equipment utilization of 91 to 94%. A minor issue was the failure of a ceiling refractory caused by the insufficient firing of support anchor tiles by a refractory manufacturer.

Official environmental measurements, conducted twice during these campaigns, confirmed the process to be more environmentally friendly with higher energy efficiency than conventional ironmaking processes. The advantage was also confirmed by the Minnesota Pollution Control Agency4)and the U.S. Department of Energy.

The following summarizes the features of the ITmk3 process.

- The process is simple.

- It allows the direct use of low grade materials (e.g., fine ore and fuel coal with neither sintering nor

coking).

- It is highly energy efficient.

- It has a low environmental load.

- It facilitates the adjustment of production by starting and stopping.

- The facility cost is low.

- Most of the equipment involved in the process has been industrially proven with high reliability.

- The plant is easy to operate, without a need for handling molten iron, which is unprecedented in ironmaking processes; so operators with mining companies can run the plant in the same manner as they run a pelletizing plant.

The granular iron produced by the large pilot plant (Fig. 12) was received well by large EAF based steel makers in the U.S. and was used as a raw

material for their steel products, such as sheet, plate

and special rods. The granular iron, with its ease of melting in EAFs, increased the furnace productivity by 5 to 8% compared with conventionally used pig-iron. Thus the ITmk3 was demonstrated to be superior, not only in its ironmaking process, but also in its product, granular iron. The granular iron, which is to be continuously charged into EAFs, will further increase the productivity and energy consumption of the steelmaking process.

The following are the features of granular iron. - It has a 2 - 4% carbon content.

- It is a clean iron with no impurities such as copper and nickel, which adversely affect the steelmaking process.

- It has a large specific gravity.

- It is easy to melt with a low melting point and high thermal conductivity.

- It is of an appropriate size for charging continuously into steelmaking furnaces.

- It has a size that is easy to handle.

- Unlike other reduced iron and hot briquette iron (HBI), the iron is completely reduced.

- Unlike other reduced iron and hot briquette iron (HBI), it does not reoxidize and ignite a fire.

- Unlike other reduced iron and hot briquette iron (HBI), it does not contain a gangue constituent.

In the U.S., granular iron is referred to as "iron nuggets," after gold nuggets.

3.3 Construction of commercial plants

The success of the large pilot plant immediately led to planning the construction of the first commercial plant. The Mesabi Iron Range, the largest ore mine in North America, lies from east to west, about 100km north of Lake Superior. There are many beneficiation/ pelletizing plants in this area. One of them is the plant run by LTV Mine, which closed in 2002 due to the steel recession. With this prospective site in mind, we have begun to work toward obtaining an environmental permit to construct a commercial plant (Fig. 13).

In 2007, stimulated by the recovering demand for steel, Steel Dynamics, Inc. decided to construct its first commercial plant with a capacity of 500 thousand tonnes/year of granular iron to secure a clean iron source. This project was co-financed with Kobe Steel. Kobe Steel's role included the provision of the process under license, engineering, major equipment and instructors. Steel Dynamics, Inc. agreed to accept all the granular iron produced and use it for their own EAFs. The construction of the commercial plant began in June 2007, and production started in 2010 (Fig. 14).

The construction of another commercial plant in Michigan, in the U.S., is being planned in collaboration with Cleveland-Cliffs Inc. (currently, Cliffs Natural Resources), one of the partners in collaborative development. Efforts to obtain an environmental permit are underway. Commercial plants are also being planned in many other countries, including Kazakhstan, India and Ukraine.

4. Bu siness model

Granular iron manufacturing is a process suitable for locations adjacent to ore mines. The process converts iron ore, the major raw material, into value additive granular iron. The operation is similar to the conventional pelletization. The process also removes unwanted oxygen and gangue minerals contained in iron ore and pellets, allowing the shipment to steel mills of a product consisting essentially of iron. Unnecessary oxygen and gangue minerals account for about 40% of ore weight. Thus the new process decreases the shipping weight and significantly reduces CO2emissions during shipment. The steel mills that receive the granular iron can enjoy the benefit of granular iron that generates no slag and decreases the cost associated

with the treatment of slag.

In the U.S., EAFs account for 63% of steelmaking, significantly exceeding the amount made by the blast furnace - converter method. However, the quality of scrap, the major raw material for EAFs, has become more degraded year by year, and securing clean iron source has become a major concern for EAF based steel makers. Clean iron source such as pig-iron and HBI, on the other hand, is almost totally dependent on imports from other countries, such as Venezuela, Brazil, Ukraine and Russia. Thus, US EAF makers are subject to supply instability and large price variations. These issues in the U.S. can be resolved by the prevalence of granular ironmaking plants.

In the U.S., most ore mines are found in the Mesabi Iron Range, to the north of the Great Lakes. Therefore, many steel makers are located in the area around the Great Lakes. They also import about ten million tonnes of clean iron source every year. The iron source is landed at New Orleans in the south and transferred upstream on the Mississippi River at a high transportation cost. The prevalence of ITmk3 plants around the Mesabi Iron Range, in the area around the Great Lakes, is expected to replace imported iron source, including scrap, with granular iron.

The following are the advantages to each sector of the industry that hav e been brought about by granular iron and granular ironmaking plants.

1) Mining sector

- Mining companies can make granular iron, which is much more value additive than conventional iron ore and pellets.

- Mining companies can expand their customer bases to EAF based steel mills in addition to blast furnace based integrated steel mills.

- Allowing the use of low grade ore will extend the lives of mines.

- The new process is feasible even for small scale mines. 2) EAF based steel manufacturers

- Use of granular iron improv es the productiv ity and energy efficiency of the steelmaking process.

- The manufacturers can secure the source for clean iron.

- Granular iron allows conversion to higher end steel products.

- Installing granular ironmaking plants in steel mills allows the use of hot granular iron, which further increases energy efficiency.

3) Blast furnace based steel manufacturers

- The new process does not require equipment with

a high environmental load, such as coke ovens and sinter plants.

- The new process allows the use of low grade materials.

- Ironmaking by the new process requires a small capital investment.

- The new process facilitates production adjustment.

- Granular iron production overseas enables the offsetting of CO2.

- Granular iron decreases the cost and CO2 emissions associated with transportation, compared with iron ore and pellets.

- Granular iron generates less slag than do iron ore and pellets.

Conclusions

The application of ITmk3 has just begun. In the same manner as blast furnaces have evolved for over a hundred years, ITmk3 is expected to expand

its applicability from granular ironmaking to, for example, molten ironmaking and low temperature ironmaking. Kobe Steel will continue its efforts in the research and development of these new processes.

1) Ko-ichiro Ohno et al. : "Steel Research," 74 (2003), pp. 5-8.

2) Taichi Murakami, et al. : CAMP-ISIJ Vol.12 (1999), p. 247.

3) S. Meissner et al. : The 11th Japan-Germany Seminar on

Fundamentals of Iron and Steelmaking, Reduction and Meltdown

of Pellets in the ITmk3 Process, (2002), p. 6.

4) Larry Lehtinen : Mesabi Nugget Research Project, United States

Department of Energy (2005).

我国高炉喷煤技术的现状及发展趋势

邯钢1000m3高炉提高喷煤比的探索 刘伟,樊泽安,王飞,徐俊杰 (河北钢铁集团邯郸钢铁公司炼铁部,河北邯郸056015) 摘要:邯钢4#高炉(有效容积1000m3)经过不断探索,加强原燃料管理、高炉的操作和维护,使喷煤比逐月提高、焦比和综合焦比不断下降。喷煤比由2008年的130.6 kg/t提高到2009年6月的163.1 kg/t,焦比由361kg/t下降到了305kg/t,综合焦比由524kg/t下降到了500kg/t,取得了良好的经济效益。 关键词:高炉;喷煤比;探索 引言 邯钢4#高炉有效容积917m3,2007年、2008年虽然炉况长期稳定顺行,但由于燃料变化比较大,有时甚至一天就变换数次焦炭,各项指标未达到最好水平,平均日产2600t上下,一级品率70%,焦比361kg/t,煤比130kg/t,焦丁比16kg/t风温1100℃,平均[Si]0.61%。进入2009年以来,4#高炉以“低耗高产”举措应对当前市场挑战,进一步探索好的经济技术指标成效显著,通过监督改善原燃料质量、适时调整煤气流分布、降低入炉焦比、提高富氧、增加喷煤、高风温协调互补、适当提高炉渣碱度等措施,基本实现了全捣固焦冶炼的长期稳定顺行,并实施了低硅冶炼,取得了很好的经济技术指标。2009年4月以来,平均日产达到2700t以上,利用系数达到3.0,一级品率93.45%,焦比降到305kg/t,煤(全无烟煤)比达到160kg/t以上,中焦比达到18kg/t,焦丁比达到16kg/t,风温达到1135℃,平均[Si]达到0.43%以下。通过优化高炉操作技术经过不断实践和探索,在喷吹全无烟煤的情况下煤比达到160kg/t以上实属难得(见表1)。 表1 4高炉生产指标 利用系/t. (m-2. d-1) 煤 比 /kg.t-1 入 炉焦比 /kg.d-1 焦 丁比 /kg.d-1 中 焦比 /kg.d-1 风 温/℃ R 2 [ Si]/% 20 08 2.88 6 1 30.6 361 14 20 1 107 1 .15 .61 20 09.4 3.0 1 51.7 327 16 18 1 132 1 .13 .44 20 3.001308 17 18 110

北欧国家高炉炼铁技术发展趋势

北欧国家高炉炼铁技术发展趋势 1 技术发展 芬兰鲁基(Ruukki)公司的1号高炉于2010年大修,2号高炉将于2011年大修。另外,2011年烧结厂关闭后,这两座高炉将全部使用球团矿冶炼。 在钢铁联合企业,高炉炼铁是能耗最高的环节。为了保持竞争力,必须减少高炉能耗和还原剂的使用。例如,鲁基和瑞典欧维克(Ovako)公司开发了喷吹重油技术来降低焦比,而瑞典SSAB公司乌克瑟勒松德(Oxelosund)厂采用了氧煤喷枪。同时,由于使用了高品位的铁矿石,北欧高炉普遍实现了低渣量冶炼。 2 氧煤喷枪 喷吹燃料代替部分焦炭,可以大幅度提高高炉利用系数和能源效率。喷吹燃料的高效燃烧是根本性的,是高喷吹量的主要问题。为了改善煤的燃烧,瑞典国家冶金研究院于20世纪90年代初开发了氧煤喷枪。通过单风口喷吹试验,SSAB公司乌克瑟勒松德厂4号高炉全部更换为氧煤喷枪。氧煤枪是内管走煤粉、外管通旋流氧气的同轴套管式直管,氧气对枪管同时起冷却作用。单风口大量喷煤试验表明燃烧十分稳定。乌克瑟勒松德4号高炉换成氧煤枪后,喷煤量由35kg/t增加到喷煤系统最大能力135kg/t。SSAB报告显示,在没有炉顶加压和没有无料钟布料条件下,高炉操作稳定,燃料比(煤+焦)较低,约为465kg/t。另外,由于减少了炉尘量,电除尘效果得到改善,高炉透气性提高。 试验高炉 1997年瑞典矿业公司(LKAB)投资500万欧元,在位于吕勒奥市的瑞典国家冶金研究院建造了试验高炉,这也是北欧研发投入最大的项目。该试验高炉工作容积为9立方米,日产铁水35吨。虽然当时建造试验高炉的目的只是为了LKAB公司内部球团的研究开发,但经过5个炉役的试验,其潜能就得到了发挥。LKAB公司和客户以及其他厂商(包括北欧和欧盟国家)在此做了大量研发项目的试验,包括矿石、焦炭、新型无料钟炉顶、高喷油和富氧、杂料喷吹、测量技术等,至今共进行了25个炉役的试验,每次试验平均运行8个星期。 风口喷吹造渣剂 风口喷吹碱性造渣剂是很有意义的技术开发,工作人员对喷吹高炉炉尘和转炉渣进行了实验室研究和半工业试验。 工作人员在试验高炉和SSAB公司吕勒奥3号高炉上进行了高炉炉尘喷吹试验,主要目的是为了循环利用和回收炉尘中的碳等能源。尽管存在管道磨损问题,但试验表明了该技术的可行性和有效性。喷吹转炉渣时,沿高炉高度方向,从炉腹到风口,炉渣的化学性能得到改善,特别是在使用高铁球团的低渣量冶炼时更是如此。通过风口喷吹造渣剂可以消除极端炉渣成分不合理而对高炉操作产生的影响。煤粉中的酸性灰分在回旋区外围形成不透液的凝固层,阻碍风口高度的煤气流分布。 同样,在使用高铁球团时加入石灰石和其他碱性熔剂,由于炉渣碱度特别高,炉腹渣的黏度和熔点会升高,也影响气流分布。通过喷吹转炉渣和其他碱性物料,可调节高炉炉渣成分,消除风口酸性渣和炉腹碱性渣的极端状况。 在LKAB试验高炉上成功进行了转炉渣喷吹试验,吨铁喷吹量为36.9kg,取得了渣比从136kg/t降低到101kg/t、焦比下降11kg/t的良好效果。同时,铁水硅含量降低了28%,并保持稳定。此外,排碱量和铁水硫含量并未受到明显影响。研究表明,与单独喷煤相比,煤粉和转炉渣混合喷吹会使回旋区疏松、深度变长。影响大规模试验的因素是须将大量转炉渣磨细。 2 含铁原料有效利用 目前北欧国家炼铁所用的铁矿石绝大部分来自瑞典LKAB公司位于拉普兰地区(Lapland)的高品位磁铁矿,该矿区的大规模开采始于20世纪初期,球团矿生产始于1955

我国钢铁工业主要技术发展方向_王国栋(上)

世界金属导报/2017年/12月/5日/第F01版 我国钢铁工业主要技术发展方向 王国栋 编者按:本报今年11月21日第44期刊登了对中国工程院院士王国栋的专访。王院士在访谈中就钢铁工业技术发展方向、存在的问题、解决问题的途径等进行了系统阐述。本文是对上文中提出的钢铁工业应当主要把握的技术发展方向的进一步深化,详细介绍了11个钢铁技术发展方向。 钢铁工业作为最主要的原材料工业,最根本任务就是以最低的资源能源消耗,以最低的环境生态负荷,以最高的效率和劳动生产率向社会提供足够数量且质量优良的高性能钢铁产品,满足社会发展、国家安全、人民生活的需求。要完成这样一个任务,我认为,钢铁工业应当把握以下几个主要技术发展方向: 1流程创新绿色发展 1.1钢铁生产全流程一体化控制 钢铁工业是典型的流程工业,最终产品质量的优劣,是由全流程的各个环节共同确定的。要想获得稳定、优良的材料质量,必须针对每一个工艺环节,进行全流程、一体化控制。控制要素包括温度(含冷却速度)、变形条件、成分、夹杂物(洁净度、种类)控制水平、排放、能源消耗等等; 1)减量化、低成本、低排放的钢铁材料与生产工艺设计 谈钢铁材料开发,离不开材料开发的四面体关系。材料的“成分、工艺、组织、性能”这四个要素构成的四面体关系告诉我们,材料的工艺和成分决定材料的组织与性能。过去通常的办法是:如果材料的性能达不到要求,可以增添某一种或某几种合金元素,或者采用后续的热处理工艺进行调整。这两种办法都是“增量化”的办法,或者消耗昂贵的合金元素,或者消耗能源与资源。 但是,材料设计的绿色化新理念要求我们做到“减量化、低成本、高性能”。在钢铁材料开发过程中,我们要把这个绿色化新理念全面融入四面体关系中。要做到:①资源节约型的成分设计,尽量减少合金元素含量,或使用廉价元素代替昂贵元素;②要采用节省资源和能源、减少排放、环境友好的减量化加工工艺方法;③从市场中发现新的组织和性能需求,逆向倒推,促进工艺技术创新和新型材料的创制;④量大面广产品的升级换代和高端产品的规模化生产,都要遵循绿色化理念。由此可见,关键工艺技术的创新与开发,在新材料的开发中占据了越来越重要的地位,材料和产品开发特别要注重关键共性工艺技术的创新。 我们现在使用的钢铁材料和它们的生产工艺,是过去几十年来不断开发出来的,由于开发当时技术水平和支撑条件的限制,在节省资源和能源方面以及减少排放和污染方面考虑不周,甚至未予考虑,急切需要改进、甚至颠覆的地方很多,技术创新、提升水平的空间很大。今天,环境、生态问题已经迫在眉睫,资源、能源问题更是刻不容缓,过去几十年发展起来的技术必须进行脱胎换骨的改造与提升;另一方面,技术进步和研究条件已经发生了翻天覆地的变化,为对这些产品及其生产过程进行改造甚至重造,提供了极好的支撑条件。我们已经有条件进行这样一场革命! 2)实行“精料方针”和“源头治理” 钢铁生产过程最重要的任务就是除去钢中的杂质,生产具有必要洁净度控制的和规定化学成分的钢铁产品。现有的冶炼过程虽然对作为原料的铁矿石和作为燃料的煤炭进行了粗略的处理,仍然有大量的有害元素残留于钢中,然后在后续的炼铁、炼钢、精炼过程中一点点除去。针对这种情况,行业里提出了“精料方针”,期望在入炉冶炼之前,尽量提高原料的洁净度。但是,碍于种种条件的限制,仍然是“泥沙俱下”,大量的有害元素进入到炉中,在随后的冶炼过程中,不得不建设大量的巨型设备,采用各种复杂的工艺,一点点地去除钢中的各种有害杂质,极大地增加了冶炼的负担和

炼铁技术发展

**炼铁发展综述 摘要:**公司自2005年以来,推行稳本固基、苦练内功、转变思维、审时度势,随机应变等一系列管理理念,以提高高炉装备水平为保障,通过狠抓“精料”工作、积极探索炼铁新技术、开创性的发展炼铁新理论,以及计算机辅助管理,使炼铁生产获得了高水平发展,高炉主要技术经济指标显著改善。 关键词:炼铁管理理念技术进步精整炉料高炉装备高炉操作制度 The Development of Iron-making of**Steel Abstract: Since 2005, the implementation of ** Steel iron company is stabilization of the solid base, Obtain, change thinking,, deal with the situation and act according to circumstances and a series of management concepts in order to improve the level of equipment for the protection of blast furnace, by implementing the "concentrate materials " work , and actively explore new iron-making technology, pioneering the development of new iron-making theory, as well as computer-aided management, which makes it reach a high level development of iron production , main technical and economic indicators of blast furnace improve significantly. Key words:iron-making,management concepts,technological improvement,finishing furnace, blast furnace equipment ,blast furnace operating system 近几年,**炼铁的快速发展,引起了业界同行的关注,特别是08年金融危机来临后,**炼铁凭借其铁前低成本优势,使得**钢铁能率先走出困境,成为行业的少有赢利企业,短短几年里,高炉经济技术指标由同行垫底走向处于领先水

国内外高炉炼铁技术的发展 (2)

国内外高炉炼铁技术的发展现状和趋势 邹忠平、项钟庸、赵瑞海、罗云文 1 前言 21进入世纪以来,钢铁工业受到金融危机的冲击,世界环境有了很大的变化。随着我国钢铁产能的增加(图1),炼铁原料质量下降,资源和能源价格上扬,二氧化碳排放等问题,炼铁作为钢铁工业集中消耗能源、资源的部门首当其冲。 在德国,钢铁企业已经承诺将在2012年前比1990年降低CO 2排放量22%;在京都议定书中日本计划钢铁厂排放的CO 2量比1990年减少10.5 %。我国生铁产量已经超过世界产量的一半,必然会对我国高炉炼铁提出相应的要求。 在新世纪对炼铁技术的展望,离不开资源、能源和经济等形势的变化,这些主要课题。21世纪也是高炉炼铁“变革的世纪”,期望在新时期钢铁产业能够进入资源、能源和环境的和谐,这是确立炼铁业持续发展的重要关键,也必须从这个理念和观点展开高炉炼铁技术的研究和开发。 5296252119544955417854100576415743060393650397213178107867799460392670 97411052910721115111185212532131031489317074213662518540416471424706773787491745978527498745281097884808982098297830784278677861751 29833040010000 200003000040000500006000070000 80000900001000001994 199619982000 20022004200620082010 年份 生铁产量/万t 世界 中国日本 图1 世界、我国和日本的生铁产量 我国许多高炉已经感到当前形势的变化,并采取了相应的措施。对高炉炼铁技术发展的方向有了新的认识,为振兴炼铁工业打下了基础。为此很有必要综观世界高炉炼铁技术发展及今后的方向十分必要。 我国高炉在大型化、高效化、低排放过程中,对高炉设计、生产出现了一系

世界钢铁冶炼技术发展方向解析

进入21世纪,世界钢铁工业的发展环境发生了深刻变化。炼铁原料质量下降,资源、能源价格高涨,二氧化碳减排问题,都对钢铁制造的各个工序提出更为苛刻的要求。展望新世纪的钢铁技术,就是能够适应这样的环境变化,能综合应对资源、能源乃至环境问题的技术。其核心的课题是“促进环境保护和物质循环”,具体的方针是追求二氧化碳的减排及资源的再利用。在新时期对钢铁业的期待是以资源、能源和环境良好协调的物质循环型社会为核心,实现可持续发展。本文即从这一视点出发,对未来的新钢铁冶炼技术的可能性进行概要论述。 原料 干熄焦(CDQ)技术 随着世界性能源短缺的不断加剧,以及各国环保法律法规的进一步完善,对钢铁企业发展提出了更高的要求,具有节能、环保突出功效的干熄焦技术,成为钢铁企业焦化生产环节中一项重要技术。 干熄焦技术是使用惰性气体循环来回收热焦炭显热,回收显热后的循环气体,通过余热锅炉产生高温、高压(或中温、中压)蒸汽。在钢铁企业焦化生产环节中,这种蒸汽可以作为钢铁厂的热源,用来发电。且可避免粉尘和含有有毒、有害物质的雾气对大气环境造成污染。除此之外,它还可提高焦炭的内在质量,使高炉入炉焦比降低2%~2.5%,生铁产量提高1%。因此,已成为国家鼓励推广的项目。 当前世界各国已投产、正在施工和设计的干熄焦装置300多套。国际上以日本新日铁、JFE、德国蒂森·斯梯尔·奥托公司干熄焦为代表的技术较为先进。这些公司在扩大干熄焦装置能力、改善冷却室特性、热平衡、物料平衡、自动化、环保等方面采用了最佳化设计。 随着干熄焦技术的推广应用,干熄焦设备的高效化、大型化成为20世纪80年代中期以来的发展趋势。建设大型干熄焦装置,具有占地面积小;投资

宝钢目前炼铁技术水平及发展趋势

宝钢目前炼铁技术水平及发展趋势 李荣壬 (宝钢炼铁部) 1998、1999年是宝钢炼铁生产技术水平大踏步提高的阶段,宝钢三期建设的完成,产量放开也大大促进了炼铁技术水平的进步。目前宝钢炼铁技术水平已达世界一流,我们已经与世界上最先进的炼铁厂韩国浦项、荷兰霍戈文、日本的新日铁共同站在了世界炼铁业的前列。但是,技术进步是无止境的,科学技术上的进步体现了一个企业的竞争力和发展潜力。本文就宝钢目前炼铁先进技术水平作一评述,并就进人新世纪后,宝钢炼铁技术发展趋势作一展望。 1 宝钢目前炼铁技术评述 1.1 原料技术 1.1.1 烧结用匀矿智能混匀技术 宝钢原料场的烧结用混匀矿技术原是新日铁引进的,而这二年我们发展了混匀技术,开发了“智能混匀”技术。这个技术按预先设定的匀矿成分,由计算机对各种矿按计划混匀,并能实时调整,使烧结用匀矿质量水平大幅上升。尽管这两年大量采用廉价矿,矿种变化大,但无论匀矿堆间、堆内的σSiO 2 。、σTFe 的波动值均在较好水平,尤其是堆内。σSiO 2 已达0.16、σTFe已达0.42水平。 1.1.2 高炉喷吹用煤的集中混煤配煤技术 原料场对三座高炉的喷吹用煤的集中供煤泥煤系统目前已开通二年多(2高炉还未接上)。该系统6个供煤槽,原则上可以四、五种煤同时混配,供高炉喷吹用。目前宝钢高炉用煤均是三、四种煤混配,由于集中供煤系统定配,使得宝钢喷吹煤的配煤技术有了很大的发展,为高炉稳定供煤,炉况顺行提供了可靠保证。喷吹用配煤混煤指标我们目前不仅仅是固定碳,挥发分二种,并且已由计算机配至灰分成分保持基本不变,目前宝钢喷吹混合煤指标见表1。 表1 喷吹混合煤标准 H20 % ASH % 固定碳 % Vm % S % 热值 KJ/kg HGI 压缩度 % 休止角 度 10 9 70 20 0.4 29500 60 25 42 灰中: % CaO % SiO 2 % Al 2 O 3 % MgO % TiO 2 % K 2 O % Na 2 O % 1 3.5 2. 2 0.05 0.1 0.05 0.05 0.08 由于我们掌握了较多品种的烟煤、无烟煤喷吹技术,又有这种先进的混煤配 煤技术,可以使得高炉大喷吹发挥很好的效益,也能确保供煤的稳定。目前我们喷吹用煤每年在210万t。 1.2 烧结技术 1.2.1 低 SiO 2 高铁分烧结技术 随着高炉煤粉大喷吹同时又要求高利用系数冶炼的发展趋势,高炉需要高铁 分入炉料和低渣比。宝钢烧结矿向低SiO 2 高铁分方向发展是大势所趋。原来宝 钢烧结矿中SiO 2 含量在5.3%~5.4%,全铁含量为56%~57%。从 1998年2 月开始L行低SiO 2高铁分烧结生产实验,由于在低SiO 2 烧结原理方面和烧结操

日本高炉炼铁技术发展趋势1

日本高炉炼铁技术发展趋势 日本是世界上炼铁技术最先进的国家,也是生铁产量第二大国。日本的新日 铁和JFE产量规模排名世界第二和第三位。近几年,日本的高炉炼铁出现了以下一些新趋势。 一、高炉的大型化 日本在高炉大型化方面远远走在世界前列。日本目前运行的高炉为28座,其中4000m3以上的高炉达到22座,5000m3以上的有12座,平均炉容已达到4050m3。新日铁大分厂1号、2号高炉炉容为5775m3,是世界上最大的高炉。日本的大型高炉中,新建的很少,除2004年9月29日投产的住友公司鹿岛厂新1号高炉(5370m3)是日本近25年来唯一新建的大型高炉外,其余均是通过大修 进行扩容的。日本4000m3以上高炉统计见表1。 3 二、高炉的长寿技术 日本高炉的长寿技术领先于世界。从20世纪80年代后,日本高炉开发了一

系列长寿技术,高炉寿命显著延长。仓敷厂2号高炉寿命达到了24年,千叶厂6号高炉寿命为20年,住友和歌山厂4号(2700m3)和5号高炉(2700m3)开炉至今已分别运行了26年和20年,现在这两座高炉仍然在生产。最近开炉的高炉一代炉役设计寿命均在25年以上。 日本部分大型高炉长寿情况见表2。 注:和歌山厂4号高炉计划2009年7月停炉,届时一代炉龄将达27年,创高炉长寿新记录。 炉身下部和炉缸是限制高炉寿命的关键部位。近年来,日本高炉在炉身下部和炉缸部位采取了一系列长寿措施,改进了炉身冷却设备和炉底砖,实现了长寿化。比如,在高炉炉底以及炉腹至炉身上部全部采用铜冷却壁,炉身冷却壁可以在炉身修补过程中进行更换;在炉底侧壁引入了制冷机以强化冷却。炉底砖的改进主要从减少微气孔以提高抗铁水浸透性和提高热传导率两方面进行,最近又开发出含TiC的碳砖。 三、高炉的大修技术 近 10年间,日本有近20座高炉大修开炉。高炉大修时采用的最主要技术除了扩大炉容、长寿技术、出铁场作业自动化外,最主要的是缩短大修工期技术。 为了尽可能减少大修造成的减产,日本高炉开发了一种可缩短大修工期的大块施工法,即将高炉按垂直方向分解为3-4段,进行整体拆除、预制和安装,拆除时将砖衬和冷却装置一起吊下,安装时预先组装好砖衬后再整体装入炉壳内,最大限度地缩短大修工期。由于采用这种大块施工法,大修工期可从130天左右缩短到90天,甚至缩短至60天。福山厂5号高炉2005年大修时采用大块施工法,大修工期仅58天。因为预先在良好的操作条件下进行炉壳焊接作业,所以不仅提高了焊接质量,而且对安全施工也有很好的效果。 另外,为了降低大修费用,扩容时主要采取扩大炉径的方式,高炉的高度基本不变。这样,高炉的基础和框架等没有太大的变化。高度低、炉径大的高炉,料柱的透气性好,有利于提高产量。

国外炼铁生产及技术进展

国外炼铁生产及技术进展 2015-11-26 11:27:00 沙永志 炼铁生产作为钢铁生产流程中的重要组成部分,是能量消耗和生产成本的主要载体,同时是污染物排放的主要工序。未来的炼铁发展状况将决定整个钢铁工业的组成、结构及产品市场竞争力。我国作为世界第一炼铁大国,今后的炼铁可持续发展取决于正确的工艺路线、先进的生产理念,以及持续的改进提高。本文试图通过对国外连铁生产及技术进展的调研,为国内炼铁同仁提供一些有益的信息和参考。 国外炼铁各工艺生产状况 世界炼铁生产工艺分为高炉工艺、直接还原工艺,熔融还原工艺。在过去的10年里,各工艺生产均取得一定进展。 高炉工艺。在过去的10余年里,在我国生铁产量高速增长的带动下,世界生铁的总量持续增加,2014年全球高炉炼铁的产量为11.795 亿吨,见图1。国外生铁总产量基本维持不变,2014年为4.679亿吨,占39.67%;我国为7.116亿吨,占60.33%。 新建高炉的大型化仍是发展趋势。韩国浦项建成世界最大的6000m3高炉。但行业普遍认识到,在原燃料质量下降和频繁波动的情况下,大型高炉的适应能力存在不足。 直接还原工艺。据美国Midrex公司统计,世界直接还原铁的生产自上世纪70年代以来,总体保持增长趋势,2013年产量为7522万吨。生产的工艺分为气基和煤基,其中气基占78.8%,煤基占21.2%。 2014年,全球直接还原铁产量为6051.9万吨(国际钢协统计,占87%),其中最大生产国是印度,产量为1806.7万吨。 直接还原工艺的一个新进展是在印度JSPL的煤气化直接还原装置(MXCOL)建成投产。该装置设计能力是180万吨/年,其工艺采取的是鲁奇的煤气化炉和Midrex的竖炉相结合,将煤用高压蒸汽和氧气进行气化,生产原料气供气基竖炉使用。据报道,2014年第3季度,该装置已生产出金属化率稳定在93%的直接还原铁产品。 熔融还原工艺。2013年,全球熔融还原(Corex + Finex)装置共生产铁水730万吨。2014年1月,韩国浦项又投产了一座200万吨的Finex装置。 HIsarna工艺开发取得进展,所建的半工业试验装置(8吨/小时)自2010年起开展了4次试验,每次2个月。据报道,其结果超过期望值,煤耗已低于750kg/t。2016年计划再开展一次试验。 综合评价,在过去的10余年里,高炉、直接还原、熔融还原各工艺的产量均在增加,而高炉的产量规模和所占的比例(含我国)均远远超过了后两者。这也预示着高炉炼铁工艺的绝对优势将长期保持。 主要国家和地区的炼铁发展状况

世界钢铁冶炼技术发展方向解析剖析

进入21世纪,世界钢铁工业的发展环境发生了深刻变化。炼铁原料质量下降,资源、能源价格高涨,二氧化碳减排问题,都对钢铁制造的各个工序提出更为苛刻的要求。展望新世纪的钢铁技术,就是能够适应这样的环境变化,能综合应对资源、能源乃至环境问题的技术。其核心的课题是“促进环境保护和物质循环”,具体的方针是追求二氧化碳的减排及资源的再利用。在新时期对钢铁业的期待是以资源、能源和环境良好协调的物质循环型社会为核心,实现可持续发展。本文即从这一视点出发,对未来的新钢铁冶炼技术的可能性进行概要论述。 原料 干熄焦(CDQ技术 随着世界性能源短缺的不断加剧,以及各国环保法律法规的进一步完善,对钢铁企业发展提出了更高的要求,具有节能、环保突出功效的干熄焦技术,成为钢铁企业焦化生产环节中一项重要技术。 干熄焦技术是使用惰性气体循环来回收热焦炭显热,回收显热后的循环气体,通过余热锅炉产生高温、高压(或中温、中压蒸汽。在钢铁企业焦化生产环节中,这种蒸汽可以作为钢铁厂的热源,用来发电。且可避免粉尘和含有有毒、有害物质的雾气对大气环境造成污染。除此之外,它还可提高焦炭的内在质量,使高炉入炉焦比降低2%~2.5%,生铁产量提高1%。因此,已成为国家鼓励推广的项目。 当前世界各国已投产、正在施工和设计的干熄焦装置300多套。国际上以日本新日铁、JFE、德国蒂森·斯梯尔·奥托公司干熄焦为代表的技术较为先进。这些公司在扩大干熄焦装置能力、改善冷却室特性、热平衡、物料平衡、自动化、环保等方面采用了最佳化设计。 随着干熄焦技术的推广应用,干熄焦设备的高效化、大型化成为20世纪80年代中期以来的发展趋势。建设大型干熄焦装置,具有占地面积小;投资和运行费用低;

相关文档
相关文档 最新文档