建筑毕业设计论文

建筑毕业设计论文
建筑毕业设计论文

摘要

此次毕业设计,设计的是东立一号楼施工图纸,建筑面积为8382.85㎡,底层建筑面积1089.72㎡,建筑层数:地上七层。层高:一层商服层高3.6m二层商服层高3.0m住宅3—7层层高3.0m总建筑高度21.90m。

施工组织设计的内容包括编制依据、工程概况、施工部署、施工进度计划、施工准备与资源配置计划、主要施工方案、进度管理计划、质量管理计划、安全管计划、季节性施工、施工现场平面布置图等。本次使用工期定额是全国统一建筑安装工程工期定额(2000)。

关键词:施工组织组织管理质量保证施工方案

Abstract

his graduation design is a design of Dongli building construction drawings, construction area of 8382.85 square meters, the building area of 1089.72 square meters, building floors: seven floors on the ground. Storey: a business suit, storey 3.6m, two storey business clothes, 3.0m storey house, 3 - 7, high 3.0m, high building height 21.90m.

The construction organization design content including the basis for preparing projectprofiles construction deployment, construction schedule, construction preparation and planning, resource allocation scheme, main construction schedule management plan, quality management plan, safety management plan, seasonal construction, construction site layout etc.. The quota for the construction period is the national construction and installation period quota (2000).

Key words: construction organization, organization management, quality assurance, construction scheme

目录

第1章编制依据 (5)

第2章工程概况 (5)

第3章施工前的准备工作 (7)

3.1 技术准备 (7)

3.2 现场准备 (8)

3.3 劳动力准备及劳动力进场计划 (8)

3.4 主要施工机械设备准备及进场计划 (9)

第4章施工进度计划及工期保证措施 (10)

4.1 施工总进度计划 (10)

4.2 各阶段施工进度计划 (10)

4.3 保证工期措施 (10)

4.3.1 组织措施 (10)

4.3.2 各阶段施工进度计划 (10)

4.3.3 经济措施 (11)

4.3.4 技术措施 (11)

第5章施工平面规划 (13)

5.1 施工用水 (13)

5.2 施工用电 (13)

5.3 施工道路 (13)

5.4 临时布置 (13)

第6章各项管理及保证措施 (14)

6.1 工程质量方针 (14)

6.2 工程质量目标 (14)

6.3 质量保证措施 (14)

6.3.1 组织保证 (14)

6.3.2 制度保证 (15)

6.3.3 管理措施 (15)

6.4 安全生产措施 (16)

6.4.1 安全管理体系认证和安全资格 (16)

6.4.2 安全生产目标 (16)

6.4.3 安全管理体系 (16)

6.4.4 安全生产责任制 (16)

6.4.5 安全生产制度 (16)

6.4.6 保证安全生产的具体措施 (18)

6.5 环境管理和文明施工措施 (19)

6.5.1 环境管理措施 (19)

6.5.2 文明施工管理 (21)

第7章施工总平面布置 (22)

7.1 施工总平面布置总则 (22)

7.2 施工现场平面布置 (22)

7.3 施工现场总平面管理 (22)

结论 (24)

致谢 (25)

参考文献 (26)

第1章编制依据

《民用建筑设计通用》

《民用建筑热工设计规范》

《严寒和寒冷地区居住建筑节能规范》

黑龙江省地方标准《黑龙江省居住建筑节能65%设计标准》《公共建筑节能设计标准黑龙江省实施细则》

《住宅设计规范》

《住宅建筑规范》

《层面工程设计规范》

《公共建筑节能设计规范》

《建筑设计防火规范》

《公共建设标准强制性条文》

《建筑灭火器配置设计规范》

《住宅工程质量通病防控规范》

与之相关现行的国家,地方建筑设计规范,规程和规定

第2章工程概况

本工程为工程为东立一号楼。建筑面积为8382.85㎡,底层建筑面积1089.72㎡,建筑层数:地上七层。层高:一层商服层高3.6m二层商服层高3.0m住宅3—7层层高3.0m总建筑高度21.90m。钢筋混凝土框架结构,现浇混凝土无梁楼盖,标准砖砌体隔墙,抗震设计烈度六度,建筑防火分类为二类,耐火等级为二级。

住宅楼为平顶卷材防水上人屋面,普通全瓷砖楼地面,室内一般普通抹灰,刷乳胶漆,木门,塑钢窗央空调系统安装,火灾自动报警,消防自动喷淋保安,综合布线,照明器具安装,给排水系统安装齐全。

第3章施工前的准备工作

3.1技术准备

1.项目经理、管理人员名单报公司生产安全部门备查。施工人员首先应认真学习和掌握有关优质工程的质量标准和施工经验,各专业施工队应结合本工程的特点,组织学习,进行技术交底,确保优质工程。

2.参加由建设单位主持召开的图纸会审,项目部技术员在技术负责人的直接领导下,做好充分准备,最大限度地解决施工图中存在的问题,从保证质量、工期和降低成本的角度出发,提出合理化的建议,为施工顺利进行提供可靠的技术保障。

3.由上级技术主管负责人主持,公司各职能部门和项目部有关人员参加的施工方案评审会,对施工过程中各种资源的配置、施工程序、质量、工期、安全、文明施工、环境保护等指标和具体措施进行评审,为编写施工组织设计提供依据。

4.在规定时间内完成施工组织设计编制工作,并按规定审批程序审批后,报监理单位、建设单位确认。

5.施工技术交底制度和岗位责任制,签订质量责任书,实行三级技术交底制:公司总工对项目部技术负责人交底,项目部技术负责人对施工员、技术员、质量检查员交底,施工员应就工程的施工组织设计和施工工艺向作业班组进行分部分项的交底。

6.对参与项目实施及过程控制的有关人员进行培训。结合本工程争创优良工程的特点,高标准、高起点、严要求,要对施工规范、施工工艺熟练掌握。

7.项目技术负责人组织编制各分项工程的特殊工序作业指导书,实行样板引路制度。

8.认真熟悉图纸,根据施工方案、技术、安全交底的具体措施选用材料,由

技术员负责模板设计,并组织木工进行模板翻样。

9.制定材料复检计划,落实影响结构安全的试块的预配工作,并按设计要求提出配合比委托,以保证有足够的试配时间。

10.制定工程测量方案,确定测量基准点和基线的布控点,做到布点合理,观测方便,设立定位控制桩点,并加以妥善保护。

11.施工图纸及有关文件应齐全,现场水、电、气应满足连续施工要求,设备材料能保证正常施工。

12.制订新技术、新工艺、新材料应用计划,对参与管理者进行必要的培训,操作人员进行技术交底和必要的跟踪指导和验证。

13.材料部门应提前落实材料和设备的进货渠道,按施工所需材料计划,做好材料及设备的供应准备工作。

14.项目部配备必要的规范、规程、标准、相关的法律法规及管理办法等,并组织相关人员学习。

3.2现场准备

1.室内准备:在熟悉图纸的基础上,做好施工图纸的翻样工作。满足施工各阶段的要求,落实内外加工定货,合理安排各类周转材料和施工机械设备的进场时间,做到有计划、有步骤。早落实、按需进场,合理利用的管理目标。

2.室外准备:将施工现场的用水引至现场指定接通地点,供水干管管径选用φ48mm钢管。施工用电需配备1台270KVA容量的变压器,楼层施工用电采用电缆由总配电盘引出,随主体引至工作面。场内各用电支线,采用“三相五线制”配线,保护零线每隔30m做重复接地,场内分配电箱至用电设备的导线采用胶皮软线,所有机械、电器设备、开关箱外壳全部用保护零线连接。确保现场水、电满足连续施工要求,合理安排施工顺序,避免各工种交叉作业的干扰。

3.施工道路:现场内设置环形施工临时道路,道路宽4.5m,150mm厚卵石混土路面,高出自然地面200mm,下部300mm厚素土夯实,保证雨天的正常通行,办公区内设1.5m宽砖铺人行道。

3.3劳动力准备及劳动力进场计划

劳动力组织由项目部与公司协调统一调配解决,基础及主体施工时每个施工段成立混合作业队,包括:木工、钢筋工、砼工、普工等工种;装饰施工阶段成立:抹灰、贴砖、油漆等专业队,凡参加本工程施工生产的人员,分别对其进行安全生产和质量意识教育,按企业规章制度严格管理。

主要劳动力以具有同类工程施工经验的施工队伍,并在全公司范围内统一协调及优化配置劳动力,实行“择优上岗”的竞争机制,全面推行“奖优罚劣”的管理办法,从劳动力调配和劳动力管理方面保证工程各项目标的实现,具体劳动力需用量和进场时间安排详见劳动力进场计划表。

3.4主要施工机械设备准备及进场计划

机械机具准备,依据总体施工方案及施工总进度计划选择安排,主要施工机械必须经试运转合格后投入本工程使用,检验试验设备必须经校检合格后准入使用。本工程共投入施工设备30台(套),施工用电设备总功率119.7KW,电焊机总容量98.4KVA。

第4章施工进度计划及工期保证措施

4.1施工总进度计划

根据本工程招标文件规定,工程计划工期为139天。

4.2各阶段施工进度计划

见施工进度计划横道图。

4.3保证工期措施

4.3.1组织措施

1.组成精干高效的项目领导班子,确保指令畅通,运行良好。

2.公司按项目法管理组建项目部,选配具有开拓精神、经验丰富、勤奋实干、科学务实且有同类工程施工经验的工程技术和管理人员组成项目管理班子。由项目经理代表企业全面履约,全面负责该工程实施过程中的组织、指挥、管理、协调和控制等工作。

3.建立生产例会制度:检查上周工程施工进度计划落实情况,安排本周施工进度计划。协调项目部各部门之间的工作关系,使项目部各项工作保持正常运行,确保按期完成施工任务。

4.做好施工准备工作,拟定施工准备计划,专人逐项落实,确保准备工作到位。

4.3.2管理措施

1.分别编制各种进度计划,组建项目进度计划管理系统,使进度计划管理始终处于良好的运行和监控状态。

2.优化施工进度方案,对多种进度计划方案进行对比、择优。在确保工程质量、文明施工、并且合理利用资源、合理的施工程序及施工方法的前提下,选用最佳的进度计划方案。

3.对施工进度实行动态管理,根据资源配置和劳动力状况及时对进度偏差采取

纠偏措施,使施工进度始终处于受控状态。

4.选择合理的劳务分包模式和物资采购模式,避免劳务分包和物资采购对施工进度产生不利影响。

5.分析影响工程进度的风险因素,采取必要的风险防范措施,以减少进度失控风险。

6.应用计算机技术对施工进度进行动态管理,提高进度信息处理的效率,促进进度信息的交流和项目各参与方的协同工作。

4.3.3经济措施

1.在编制施工进度计划的同时,编制与施工进度计划相适应的资源需求计划,提前作好资源储备。

2.全面推行进度奖惩措施,使所有参与施工人员的奖金与施工进度、质量挂钩。

4.3.4技术措施

1.本工程采取总控制进度计划与月旬进度计划相结合的多级网络计划,对施工进度进行有效的控制和管理,并利用计算机技术对网络计划的实施进行动态管理,通过施工网络节点控制目标的实现来保证各控制点工期目标的实现,由此进一步确保总工期目标的实现。

2.采用成熟的建筑新技术、新工艺,通过新技术、新工艺的推广应用,有效的缩短各工序的施工周期。

3.根据各工序之间的逻辑关系及施工周期,科学地组织施工,统筹安排,形成各分部分项工程在时间、空间上的合理穿插;在平面、立面上的合理交叉作业,以达到缩短工期的目标。

4.每月月初,根据月进度计划向各施工班组下发当月施工任务书,使班组明确进度目标。月底结算时,按完成的工作量和质量评定结果来进行奖罚,以此调动班组的工作积极性。

5.提前落实材料资源供应计划,确保材料按期供应,避免在施工过程中出现停工待料,影响施工进度。

6.最大限度的利用机械化施工,确保施工机械的完好率、利用率。

7.采取切实可行的季节性施工措施,保证施工的连续性。

8.做好土建与安装的专业配合,避免专业配合不利而造成工期延长。

第5章施工平面规划

5.1施工用水

施工用水由业主指定水源用φ48钢管装表计量接入,然后分别接至搅拌机和建筑物附近,设6个给水阀门分别控制。

5.2施工用电

根据施工现场设备用电量计算,施工总用电量119.7KW,从业主指定位置装表计量接入,然后分别接至搅拌机、钢筋场、钢结构加工场、门架升降机、模板加工场及建筑物附近。电缆埋地敷设。

5.3施工道路

施工道路沿施工场地枝状铺设,路宽4.5m,原土碾压夯实后铺150mm厚卵石混土,以保证雨天的正常施工通行;办公室和库房前设1.5m宽砖铺人行道。

5.4临设布置

施工现场设置生产大临和现场办公室,能满足本工程施工人员居住需要。生产设施包括:办公区、钢筋场、模板加工及料具堆场和安装材料场等。施工现场大临及临设用地见大临设施一览表和临时用地表。

第6章各项管理及保证措施

6.1工程质量方针

我们的质量方针是:信守合同、保证质量,优质服务,为业主提供满意的建设工程产品。

6.2工程质量目标

质量目标:

1.工程质量合格率100%;

2.分项工程合格率100%;

3.重要分项工程优良率100%;

4.分部工程合格率100%;

5.分部工程优良率90%;

6.主体结构工程优良。

杜绝重大质量事故,无工程质量投诉。

6.3质量保证措施

6.3.1组织保证

按公司质量控制程序文件要求组成项目经理部,其组织机构为项目经理、项目副经理、技术负责人及四部一室(工程部、技术质量部、物质设备部、经营部、办公室)。

项目经理代表公司对项目全面负责,是工程质量的第一负责人,在项目上实施公司的质量方针和“质量、工期、服务”的企业宗旨,全面履行施工合同。技术负责人对项目经理负责,协助项目经理监管项目质量保证体系的运行,主管项目的技术、质量管理工作。下属各专业项目部按照对应原则设立四组一室。两级项目部分工明确、相互配合,共同保证GB/T19002-ISO9002 质量标准中各个质量要素都得到有力的控制。

6.3.2制度保证

1.端正经营思想,切实做到“六不准”:

1) 没有设计图纸和施工组织设计或作业设计不准施工;

2) 自行采购的工程材料、配件,未经监理工程师确认和业主批准,不准采购;

3) 材料、配件无合格证和材料不按规定检验或复检不合格的,不准使用(由业主下属的材料部门提供的材料不合格品或无合格证者,除不准使用外,还应及时报告监理工程师和业主)。

4) 上道工序质量检查不合格的不准转入下道工序施工;

5) 各类综合管道(含其保温)、设备安装前,未试做或制样且经监理工程师确认者,不准进行施工;

6) 对质量有重要影响的特殊工作人员未经培训并取得上岗证者,不准上岗。

2.坚持质量一票否决制度

坚持质量一票否决制度,其具体要求是:对不合格的工序、工件必须坚持返工;质量不合格的工件,不准上报工作量,同时对不合格工序、工件不准转入下道工序。

3.落实各级质量责任制

项目经理部和各设备制作厂及二级项目部的项目经理是所承包工程的第一责任人。设备制作厂经理对承建的制作工程质量负责,工长对部件加工质量负责,班组长对加工工序质量负责。

6.3.3管理措施

1.施工前进行质量策划

坚持质量目标管理,工程施工前各专业项目部确定本单位施工项目的质量目标及要求,结合工程特点,编制出针对性、操作性强的项目质量计划;做好施工组织设计和关键工序、特殊工序的施工作业设计的编制和审定工作。

2.严格按照相关技术标准指导施工

所有工程实体施工、验评严格按照国家和主管部门及设备供应商所颁发的现行技术规范标准进行工作。

6.4安全生产措施

6.4.1安全管理体系认证和安全资格

我公司已通过了职业健康安全和环境管理体系认证,管理体系运行正常,效果良好。

我单位具备建筑业安全资格证书,年检合格。在施工中按照安全认证的标准,严格规范行为,保证施工工地安全达标。

6.4.2安全生产目标

1.杜绝重大伤亡事故、交通事故、机械事故和火灾事故的发生,千人负伤率控制在3‰以内。

2.创建安全达标工地。

6.4.3安全管理体系

认真贯彻执行“安全第一,预防为主”的安全生产方针,建立以项目经理为主,项目副经理、技术负责人及有关职能部门组成的安全领导小组。项目经理要亲自抓安全生产管理工作,使安全管理体系正常运行。

6.4.4安全生产责任制

项目经理、项目技术负责人、安全员、施工员、班组长、操作人员必须按照《安全生产管理条例》认真执行,以身作则抓好安全生产和劳动保护工作。为严肃安全纪律,对违纪、违规、违章现象进行批评教育或对当事人进行处分。

6.4.5安全生产制度

1.安全生产教育制度

(1)工程开工前,由项目经理组织项目管理人员和广大职工群众对安全生产重要性、安全生产方针、政策、法规进行教育,以增强关心人、保护人的责任感,树立牢固的群众观点。

(2)工程开工后,全体职工必须按规定学时进行安全培训教育,使其掌握安全基本知识。

(3)项目经理、项目技术负责人、施工员对新进场人员进行工程概况、安全防护、工程进度以及建筑常识教育、公司劳动制度、劳保制度、各种操作规程的学习,并有学习人员登记签字手续。

(4)在施工过程中,结合本工程特点及工种专业特点,进行各工种岗位专业安全技术知识教育,经考试合格后,持证上岗。

(5)新工人包括新入场的合同工、外协队伍人员和实习代培人员,一个不漏的进行三级教育,未接受入场教育者不得上岗。

(6)项目部必须每月根据当月安全生产情况进行安全检查分析、总结,要求采取各种技术措施预防安全事故的发生。

(7)周一安全例会制:项目部每周一组织全体施工人员进行安全教育,对上周安

全方面存在的问题进行总结,对本周的安全重点和注意事项做必要的交底。

(8)各种新材料、新工艺、新技术施工前必须由项目部技术负责人,专职安全员对操作者进行安全教育,并经考核合格后,方可上岗操作。

(9)安全技术交底制:管理人员需根据工程特点、环境、危险程度,以及预计可能出现的危险因素,进行书面的交底,交底人和被交底人都必须签字。

(10)班前检查制:工长组织监督和检查施工方法,班组长或兼职安全员必须根据作业环境和工作特点向作业人员交待安全生产措施及应注意的事项,并做好记录,履行签字手续。

(11)外脚手架和机械设备实行验收制度,凡不经验收的一律不准投入使用。

(12)持证上岗制:特殊工种必须有上岗操作证,严禁无证上岗。

(13)危急情况停工制:一旦出现危及职工生命安全险情,要立即停工,同时

上报,及时采取措施排除险情。

2.安全生产检查制度

(1)公司每月组织一次项目部安全施工的全面检查,并对检查内容评分,进行定量、定性的安全评价,检查结果以书面形式下发项目部负责人,要求对存在隐患部位限期整改,并将整改结果上报公司。

(2)项目部每周六由专业技术人员、安全技术人员和有实际操作维修能力的工人组成安全检查小组,对本工程的脚手架、电气、、机械设备安全问题或施工中存在的普遍性安全问题进行检查一次。

(3)项目部每半个月由安全领导小组对近期存在安全隐患,替在安全问题进行分析总结,提出安全技术防制措施。

(4)各班组每天施工前、施工后进行安全检查,发生问题及时上报有关人员。

(5)专职安全员及安全值班人员严格遵守巡回安全检查制度。

(6)检查中发现的隐患问题应进行登记,发出隐患通知书,要求限期整改,并作死循环处理记录。

(7)项目部安全检查中发现重大安全隐患,应在24小时内上报公司领导,并停止该部位的施工。

6.4.6保证安全生产的具体措施

根据公司确定的安全管理目标,该工程确保安全检查达到“省级文明工地”要求。

1.工程施工安全管理措施

(1)项目经理负责整个现场的安全工作。各管理人员认真按各自的生产责任制履行自己的职责,严格执行各项管理制度、安全生产管理条理,落实施工组织设计措施规定的有关安全措施。

(2)坚持开展“三违”和“三不伤害”宣传活动。项目经理、施工员在安排施工生产任务的同时,必须做好分部分项工程的安全技术交底工作,现场配置专职安全员来加强现场管理工作,发挥监督、检查的作用。安全检查标准按JGJ59—99《建筑施工安全检查标准》执行。

(3)对安全生产设施进行必要的合理投入,重要劳动防护用品必须购买定点厂家的产品。要使所有员工会正确使用个人安全防护用品和安全防护措施。

(4)防护设施的变动必须经项目经理部安全员批准,变动后要有相应的防护措施,作业完成后按原标准恢复,所有资料由项目部安全员管理。

(5)在施工过程中对安全薄弱环节要予以重点控制,凡设备性能不符合安全的一律不准使用。

(6)公司每月20~25日对项目部进行安全检查。项目经理部每周组织一次现场安全检查,班组坚持每天班前进行安全检查并做好记录。检查出的隐患要定人、定时间、定措施整改。

(7)坚持每周一的安全例会,做到不流于形式。

(8)以各种形式,加强对职工的安全教育,提高职工的安全意识,提高职工的自我防护能力。

(9)安全技术交底制:管理人员需根据工程特点、环境、危险程度,预计可能出现的危险因素,进行书面的交底,交底人和被交底人都必须签字。

(10)班前检查制:工长组织监督和检查施工方法,班组长或安全员必须根据作业环境和工作特点向作业人员交待安全生产措施及应注意事项,并做好记录,履行签字手续。

(11)外脚手架和机械设备实行验收制度,凡不经验收的一律不准投入使用。

(12)持证上岗:特殊工种必须有上岗操作证,严禁无证上岗。

(13)危急情况停工制:一旦出现危及职工生命安全险情,要立即停工,同时上报,及时采取措施排除险情。

6.5环境管理和文明施工措施

环境保护是每个公民应尽的义务,建筑企业作为对环境影响较大的组织,应该在日常活动中加强环境保护。我公司已通过环境管理体系认证,经过一年多的运行,管理体系已日臻完善,步入了良性运行的轨道。项目部将严格按照GB/T24001-2004标准建立本项目的环境管理体系,并确保体系的良好运行。

6.5.1环境管理措施

1.防止扬尘的措施

(1)清理施工垃圾时,使用封闭的专用垃圾道或采用容器吊运,严禁随意临空抛撒造成扬尘,施工垃圾要及时清运,清运时,适量洒水减少扬尘。

(2)细粉、散物料尽量采用车或罐、箱封闭存放并严密遮盖,卸运时采用有效措施,避免扬尘。

(3)通向施工现场的道路应有专人清扫,泥土及时清运,保持道路畅通,车辆不带泥砂出场。

(4)各作业面由班组长负责,实行工完场清。

(5)现场设1台大功率自动上热水电炉,保证现场开水供应,禁止使用小煤炉烧水,防止产生烟尘。

(6)杜绝操作班组燃烧木柴取暖和焚烧有毒物品。

2.防止水污染

(1)现场污水必须排向污水池,严禁污水任意乱流,污染环境。

(2)搅拌机及运输清洗处设置沉淀池,排放的废水要排入沉淀池内,经二次沉

淀后,重复利用,现场污水经沉淀后排入业主指定的污水管线进入厂区污水处理厂。

(3)厕所设有防渗措施的化粪池,食堂设隔油池。

(4)生活污水经沉淀达到二级排放标准后排入厂区污水处理厂或市政管道。

3防止施工噪声污染

(1)建立健全控制人为噪声的管理制度,进行必要的噪音监测,将施工噪声纳入项目部考核指标。

(2)严格控制作业时间,夜间施工一般不超过22点,特殊连续作业,应与业主和监理协商,同意后方可施工。

(3)噪音大的机械要用隔声泰柏板围护,降低机械噪声的扩散,砼振捣时采用ZX50高频插入式振捣器,可提高振捣效率,减少振捣时间以控制噪音的扩散和持续

时间。

4建筑废弃物管理

(1)固体废弃物要进行分类管理,施工现场设置分类垃圾箱,垃圾分类堆放,不可回收的固体废弃物要定期清理,按照业主要求,及时清运到垃圾场。可回收的固体废弃物要及时回收利用。生活垃圾和建筑垃圾严禁乱扔、乱撒,以免造成二次污染。

(2)禁止将有毒有害废弃物用作土方回填,以免污染地下水和环境。

5易燃、易爆物品和油品、化学品的管理

(1)储存:储存在专用仓库内,仓库地面要有防渗措施。分类存放,设专人管理,并建立台帐,定期清点。

(2)领用:对领用人、领用品、领用数量、领用日期进行登记,控制领用数量。

(3)机动车用油在加油站加注,现场尽量减少油品储存。

(4)机械设备维修时,要在操作地点铺细砂和油毡,防止油品污染土地。清擦

零件的棉纱要集中回收,不得随意丢弃。

6降耗节能措施

建筑学专业绿色建筑毕业论文外文文献翻译及原文

毕业设计(论文)外文文献翻译 文献、资料中文题目:绿色建筑 文献、资料英文题目: 文献、资料来源: 文献、资料发表(出版)日期: 院(部): 专业:建筑学 班级: 姓名: 学号: 指导教师: 翻译日期: 2017.02.14

原文: DOCTORAL FORUM NA TIONAL JOURNAL FOR PUBLISHING AND MENTORING DOCTORAL STUDENT RESEARCH VOLUME 7, NUMBER 1, 2010 Green buildings Priscilla D. Johnson PhD Student in Educational Leadership Whitlowe R. Green College of Education Prairie View A&M University Prairie View, Texas William Allan Kritsonis, PhD Professor and Faculty Mentor PhD Program in Educational Leadership Whitlowe R. Green College of Education Prairie View A&M University Member of the Texas A&M University System Prairie View, Texas Hall of Honor (2008) William H. Parker Leadership Academy, Graduate School Prairie View A&M University Member of the Texas A&M University System Prairie View, Texas Visiting Lecturer (2005) Oxford Round Table University of Oxford Oxford, England Distinguished Alumnus (2004) College of Education and Professional Studies Central Washington University Ellensberg, Washington Abstract: Green building refers to do its best to maximize conservation of resources (energy, land, water, and wood),protecting the environment and reduce pollution in its life cycle. Provide people with healthy, appropriate and efficient use of space, and nature in harmony symbiosis buildings. I described more details of green building design’notion, green building’design, as well as the significance of the concept of green building and improve the effectiveness analysis of the external effects of green building measures, Key words: green buildings; protect the ecology; signification ; analysing the effects

建筑学毕业设计开题报告

建筑学毕业设计开题报告 开题报告是指开题者对科研课题的一种文字说明材料。这是一种新的应用写作文体,这种文字体裁是随着现代科学研究活动计划性的增强和科研选题程序化管理的需要而产生的。下面是小编整理的建筑学毕业设计开题报告范文,希望对你有所帮助! 随着建筑工程技术的不断提升,各类超高层、异形结构等建筑受到了国内城市的广泛欢迎,然而这类建筑也给建筑施工安全管理工作带来了一定的困难。BIM技术因其具备可视化、动态化、协调性、模拟性等优势特征,其对建筑项目施工安全管理工作具有十分重要的指导作用。相比于以往的建筑施工安全管理,应用BIM技术能够促使项目管理人们能够及时直观的发现施工现场的安全隐患,并及时排查整改安全隐患,确保建筑施工安全。此外,应用BIM 技术,项目施工安全管理人员可以借助三维动态进行安全技术交底、安全告知、安全警示等安全教育管理工作,有利于现场施工人员更加形象的了解施工过程的安全操作方法和注意事项。由此可见,研究BIM技术在建筑施工安全管理中应用具有十分重要的意义。 1—1 可视性 BIM技术的应用可以提升建筑的可视化水平,三维建筑信息模型中包含着建筑全面的物理信息和功能信息,在建

筑施工过程中,利用BIM模型,能够方便的提取出所需的信息,这对现场安全布置,各类防护搭设提供了很大的便利。 1—2 模拟化 BIM技术可以对建筑的地质环境、裂缝、沉降等进行模拟,进而对建筑结构采取有效的防护措施,提升建筑的稳定性。BIM为建筑质量安全管理工作提供指导,不同类型建筑系统发挥了各自的建筑运行功能。在建筑项目施工前,BIM可以对存在危险性的工作进行模拟实验,例如深基坑支护施工、脚手架搭设、悬挑架搭设、吊篮施工等,从而确定最佳施工方案。 1—3 优化性 建筑工程项目的建设过程是一个不断完善优化的过程。BIM模型提供了建筑物的实际存在的信息,包括几何信息、物理信息等,利用BIM模型对建筑物进行可视化展示、协调、模拟以及优化后,从而有利于优化管理决策。 2—1 管理人员的技术水平有待提升 BIM技术在建筑施工安全管理中的应用对施工项目管理人员的专业水平和实践能力都提出了较高的要求,然而,当前建筑企业这方面的人才比较欠缺,一些年龄偏大的安全管理人员思想比较保守,对新技术的应用显得不适应,导致建筑施工安全管理工作受到一定的限制。一些建筑单位

交通工程毕业设计计算书

某省道兴化至泰州段建设工程设计 摘要:本设计为某省道兴化至泰州段建设工程设计,包括方案、路线、路基路面、排水系统以及沿线主要配套设施的设计。本工程设计速度为80km/h,本次设计包括道路平面设计, 道路纵断面设计, 道路横断面设计,路基设计,沥青路面设计,路基路面排水设计,桥涵及附属构造物设计等。 本设计的路线,纵断面设计共设3个边坡点,最大坡度为0.818%,最小坡度为0.33%。竖曲线半径分别有25000m,15000m,20000m(自己改)。路基宽度为26m,行车道宽度为3.75m,土路肩0.75m,硬路肩3m,中央分隔带3.5m。路面结构中,面层采用沥青混凝土(13cm),其中表面层采用细粒式密级配沥青混土(厚度3cm),中面层采用中粒式密级配沥青混凝土(厚度4cm),下面层采用粗粒式密级配沥青混凝土(厚度6cm);基层采用石灰土(厚度为45cm);底基层采用碎石灰土(厚度为25cm)。本路段设计桥涵2座桥,结合桥头地质情况综合考虑灌溉、排涝及地方出行的要求进行桥跨布置。 关键词:工程设计纵断面横断面路基设计沥青路面设计桥涵及附属构造物设计

Abstract:The design, construction and engineering design, including the design of programs, routes, subgrade and pavement, drainage systems, as well as along the main supporting facilities of the province Road Xinghua, Taizhou segment. This engineering design speed of 80km / h, this design includes the road graphic design, road vertical alignment design, road cross-sectional design, the design of embankment, asphalt pavement design, subgrade and pavement drainage design, bridge and subsidiary structures design. This design, too, Profile Design, 3 slope, the maximum gradient of 0.818%, the minimum slope of 0.33%. V ertical curve radius of 25000m, 15000m, 20000m (change). Roadbed width of 26m, the carriageway width of 3.75m, 0.75m soil shoulder hard shoulder 3m, the central median of 3.5m. Pavement structure, the surface layer of asphalt concrete (13cm), the surface layer is fine-grained type dense-graded asphalt mix soil (thickness 3cm) in the surface layer in grain-type dense-graded asphalt concrete (thickness 4cm), the following layer of coarse grain type dense-graded asphalt concrete (thickness 6cm); primary calcareous soil (thickness 45cm); sub-base gravel dust (thickness 25cm). The design of the sections of bridges and culverts 2 bridge, combined with the the bridgehead geological conditions considering the travel requirements of irrigation, drainage and local bridge span arrangement. Keywords:engineering design longitudinal cross-sectional roadbed design asphalt pavement design bridges and culverts and ancillary structures design

建筑工程技术毕业设计论文

. 毕业设计(论文) 题目:重庆市武隆县造纸厂职工宿舍楼建筑施工图及 施工组织设计 院 (系):建筑工程系 专业:建筑工程技术 姓名: 学号: 指导教师:

摘要 此次毕业设计,设计的是重庆市武隆县造纸厂职工楼施工图纸,建筑面积为2780.4㎡,建筑总高度为20.7m,采用框架结构,天然地基,独立柱基础。本次设计的主要内容是施工组织设计的编写。 施工组织设计的内容包括编制依据、工程概况、施工部署、施工进度计划、施工准备与资源配置计划、主要施工方案、进度管理计划、质量管理计划、安全管计划、季节性施工、施工现场平面布置图等。本次使用工期定额是全国统一建筑安装工程工期定额(2000)。 关键词:施工组织组织管理质量保证施工方案

目录 第1章编制依据 (5) 第2章工程概况 (5) 第3章施工前的准备工作 (7) 3.1 技术准备 (7) 3.2 现场准备 (8) 3.3 劳动力准备及劳动力进场计划 (8) 3.4 主要施工机械设备准备及进场计划 (9) 第4章施工进度计划及工期保证措施 (10) 4.1 施工总进度计划 (10) 4.2 各阶段施工进度计划 (10) 4.3 保证工期措施 (10) 4.3.1 组织措施 (10) 4.3.2 各阶段施工进度计划 (10) 4.3.3 经济措施 (11) 4.3.4 技术措施 (11) 第5章施工平面规划 (13) 5.1 施工用水 (13)

5.2 施工用电 (13) 5.3 施工道路 (13) 5.4 临时布置 (13) 第6章各项管理及保证措施 (14) 6.1 工程质量方针 (14) 6.2 工程质量目标 (14) 6.3 质量保证措施 (14) 6.3.1 组织保证 (14) 6.3.2 制度保证 (15) 6.3.3 管理措施 (15) 6.4 安全生产措施 (16) 6.4.1 安全管理体系认证和安全资格 (16) 6.4.2 安全生产目标 (16) 6.4.3 安全管理体系 (16) 6.4.4 安全生产责任制 (16) 6.4.5 安全生产制度 (16) 6.4.6 保证安全生产的具体措施 (18) 6.5 环境管理和文明施工措施 (19) 6.5.1 环境管理措施 (19) 6.5.2 文明施工管理 (21)

建筑学专业毕业设计调研报告1

调研报告 建筑学专业 地理位置: 南阳市卧龙轧花厂位于南阳市长江路东段。东侧紧邻南阳理工学院,北侧为家具市场,西侧有南阳理工学院教职工家属楼,南侧为常庄居民区。地理位置优越,交通方便。 现状: 南阳市卧龙轧花厂成立于一九九六年,厂区内现有六栋厂房,和一栋附属的设备用房,另有广阔的闲置空地空间,已有13年历史。主要经营收购加工,调运棉花,榨油,修配,随着经营需求的调整现在厂区已经闲置不用。厂区内部现供驾校和汽车维修使用。 场地: 厂区内部地势平坦,整体上南高北低,利于排水。现厂区内部有机井两处。市政用电接入口位于厂区西南部为,现有配电房位于西南角烟囱附近。厂区前面有住宅楼三栋楼,环境较为混乱,临街为商业。 厂房现状: 现有厂房属于建造于上世纪90年代的单层建筑厂房,结构为砖混结构,屋顶为槽型板铺装,内部有抹灰,因长期闲置无人管理,内部墙面面层多有脱落。外墙为清水砖墙,无面层处理。南侧厂房外墙面贴有面砖,内部面层也已脱落。最南部单层厂房年代较为久远,现为仓储和加工用房。内部墙面无处理,屋顶为木构架,屋顶继续修复处理。 文化创意产业发展现状: 随着我国经济的持续稳定发展,我国人民的生活水平不断提高,相应的教育水平及科研投入也在不断增长,这对加大文化创意产业的投入具有很大的意义,它可以创造适宜产业发展的良好的社会环境;同时,随着我国教育水平的提高,创意人才的增多,一方面有利于推动创意产业的发展,同时也对创意产品产生了更多的需求;另外,拥有13亿人口的大陆市场,潜力巨大,易于吸收各种创意产品;最后,我国廉价的劳动力以及低廉的生产成本也是其发展的一大优势。 创意产业是城市发展新的增长点。随着我国经济体制转轨、产业结构升级、城市功能转换,自主创新已成为国家战略。北京798,上海的M50.,南京的1865,深圳的F518等都已成为中国相当

(完整版)建筑学毕业设计(论文)

本科生毕业设计(论文)诚信承诺书 1、本人郑重地承诺所呈交的毕业设计(论文),是在指导教师的指导下严格按照学校和学院有关规定完成的。 2、本人承诺在毕业设计(论文)选题和研究内容过程中没有抄袭他人研究成果和伪造相关数据等行为,没有请人代做。 3、在毕业设计(论文)中对侵犯任何方面知识产权的行为,由本人承担相应的法律责任。 4、学校有权保留本毕业设计(论文),允许被查阅和借阅,可以将毕业设计(论文)的内容编入有关数据库进行检索或向上级有关部门送交本毕业设计(论文)。 学生(签名): 年月日

摘要 近年来,随着旅游业的发展,以名人故居所在地为核心的历史名人纪念馆也越来越被社会各界所关注。名人纪念馆被当做城市文化的重要组成部分,不仅代表着一个城市的精神面貌,同时也记载着一个城市的人文历史,展示着一个地方的历史变革,是一种宝贵的资源。通过精心设计的纪念馆不仅能让人们在参观中接触自然,改善心情,使疲惫的身体得到较好的放松,而且还能激发人们内心深处的纪念情感,与环境产生共鸣,同时放松身心去感受城市的文化内涵,唤起对这一城市或历史名人的特殊记忆,从而达到身体与心灵的净化。与此同时,名人纪念馆往往具有重要的教育意义和价值,不仅对目前生活在这座城市中的居民,而且甚至对我们未来乃至子孙后代都有着深刻的影响。因此,我们应当更加关注名人纪念馆的建设,使其成能传承城市的文脉,延续城市的记忆,乃至整个城市的象征。 在当今,城市建设如火如荼,几近疯狂。这种疯狂带来的却是表皮的不断重复,毫无城市特色可言。不过,幸运的是随着旅游业的大力推广和发展,打造特色城市,全国兴起了发掘城市历史文化的浪潮。于是开始争相挖掘各地自然人文资源,大力开发各类诸如纪念馆,名人公园,名人故居等以“纪念”为主题的设计规划。 名人故居,在世界各国都被看做是一种极其珍贵的遗产。它浓缩了一个时代的历史,镌刻着一个民族的文化记忆,是一个地方的特殊坐标,更是不可再生的人文资源,具有很高的历史文化价值,同时也是发展当地文化旅游业发展的有利因素。 关键词:历史名人纪念馆,名人故居,纪念意义,设计理念

建筑学毕业设计调研报告

课题简介及选题意义(前言):目前我国都市商业中心的规划、设计普遍存在共性的问题。因此,应打破传统的选址思路,构建人与自然和谐统一的现代化商业园区;进行人性化的商业规划和设计,建立完整的配套服务体系;注入现代商业文化理念,打造现代化的商业中心;建立起一套和谐高效的公共管理系统。我做了一系列的调研。。 这次选择这个题目(西安市长安区某小区商业综合配套建筑设计)作为毕业设计,我是这几方面考虑的: 第一,进一步认识城市设计课程。商业建筑作为一个城市的商业建筑,必定与城市,城市设计脱离不了关系,它的设计最初应是从城市出发,以解决城市出现的问题为己任。它的建设必定丰富了城市,便利城市的居民,提供居民生活的良好环境。 第二,进一不了解商业建筑,掌握更加现代化的商业建筑的手法。在学校的学习中,我们学习了很多种类型建筑的设计手法,但商业这一部分比较薄弱且不够系统,应通过这次的毕业设计去系统以下商业建筑。并总结以下建筑设计的步骤和系统的方法。 第三,进一步对商业模式的演变和现代山业存在的问题做一系列的阐述,将商业中心建设成服务人类,方便人民的服务机构,并且应具备人性化,现代化,与自然结合,融入自然,体现人本的特点。 第四,对自己的设计能力及各方面的调节能力,统筹计划的能力做一些总结,以便在以后的工作中发挥作用。 调研对象:西安市长安区党校周遍环境调研。其位于秦岭脚下,周围充满了浓厚的生活气息,城市亦城亦乡,令人舒畅。 调研目的: 商业网点是城市规划的有机组成部分,既承担着城市的商业服务,又是城市繁荣与否的标志。因此建设和发展城市商业、完善城市商业的服务功能是当今发展城市经济和构造城市风貌的重要课题。从人性化的角度看,目前我国都市商业中心的规划、设计以及服务体系普遍存在以下问题:一是商业中心的投建开发缺乏自然元素。二是商业中心的整体规划设计缺乏地下、地面、空间三维的立体式交通传输体系和人性化的配套服务体系。三是商业中心的建筑风格缺乏现代商业文化理念。四是商业中心缺乏和谐高效的公共管理系统。因此,本文针对上述问题,以全新的视觉,将人性化理念注入现代都市商业,探寻最理想的都市商业服务模式。通过实地调研进一步了解所做课题的特点和存在的问题。 本次调研的的对象为场地地貌,场地的周遍环境,周遍的人文环境,周遍居民的生活状况,商业设施,经济条件。 调研对象的现状: 区位条件:场地位于西安长安区韦区内,坐落于秦岭脚下,该地区四面环山,虽然已接近城市的边缘,但这里感觉不到郊区,农村的感觉,相反,它与城市接轨,到处体现了城市的新风尚,新面貌,而又加了写乡村的气息,亦城亦乡。 这里原是城中村改造而来的城市,在城市中穿插着农村,居民普遍的消费水平不高,在这一地带有两个大学,一个高中,为这里带来了很大的消费群体,他们的消费水平都偏低。 场地周围及其附近一带的居民数量很多,但是这里的公共设施很少,没有一个公共集散场地比如说一个大广场,休闲交流的场所,儿童游戏的场所。

道路工程毕业论文

摘要 本设计是都江堰至大邑段一级公路设计。设计部分的公路全长2928.063m,设计车速80km/h,双向四车道,有3个平曲线转角,3个竖曲线变坡点,两侧土路肩为0.75m,硬路肩为2.5m。 在本设计过程中,主要包括以下几方面的设计: 确定道路等级:依据相应技术规范,进行交通量分析,确定公路的等级以及设计需要的各种参数。 道路选线及线形设计:在地形图上选择两条合理的路线,分别进行平面、横断面、纵断面三方面的设计,比选确定符合技术、经济指标的最佳方案。 路基设计:主要内容是确定路基的边坡形状及坡度,选择合适的填料及压实标准。 排水设计:主要解决边沟和排水设施的形状和尺寸。 路面设计:通过计算车辆轴载设计两个路面方案进行比选,确定合理方案。 专题设计:挡土墙设计。 概预算部分:通过相关资料计算该公路造价。 关键词:选线;路线设计;路基;路面;挡土墙

Abstract The design is mainly a highway engineering design from DuJiangYan to DaYi section , the length of this road is 2928.063m,the design of the speed is 80km/h, it has 3 plane curve corner, 3 vertical curve, unpaved shoulder is 0.75 m, hard road shoulder is 2.5 m. The main aspects of the design of this process are like these: Ensure the grade of this road: The analysis of traffic, search corresponding technical specifications, to determine the levels of the road and the parameters of the design needed. Choose the road route and make linear design: Choose two right route in the topographic map, Then to design the layout, cross-sectional and longitudinal of the two routes in order to choose the best one. Which meets shun fitness requirements ,economy etc. Roadbed design: The main content of the roadbed design is to determine the roadbed slope form and it’s width, then to choose the appropriate packing and compacted standards. Drainage design: The design is mainly to determine the shape and the size of drainage facilities. Pavement design: Design two pavement program in order to selection based on the calculation of the axle load. The to determine the rational program. Special subject design: Retaining wall. Budget part: Mainly according to related data , calculating the cost of the road. Keywords: route route design subgrade road surface retaining wall

某建筑工程毕业设计论文

毕业论文题目建筑工程现场施工管理 所属系别: 建筑工程系 专业班级水工(2)班 姓名:夏阳 学号: 2009301232 指导老师:胡秉香 完成日期?年月日

目录 第一部分:摘要........................................................................3第二部分:关键词 (3) 第三部分:正文 ?一、浅析建筑工程现场施工技术管理措施 (4) ?二、浅谈建筑工程中的深基坑支护施工技术 (5) ?三、论建筑工程中桩基的施工技术及应用 (7) 四、论建筑工程中混凝土工程的质量检查及处理措施 (9) 五、关于工程项目全过程工程造价的控制及管理……………………10 六、关于建筑工程技术资料整理………………………………………12 第四部分:参考文献 (14) 第五部分:致谢……………………………………………………15

摘要 现场管理实际上是我们企业生产经营活动的基础。同时,它也是企业整体管理工作中最重要的组成部分。换言之,施工企业若想在日趋白热化的市场竞争中获得应得份额,就必须优化现场管理。随着我国经济体制改革的深化和社会主义市场经济体制的逐步建立,也出现了诸多的矛盾和问题。所以,建立良好的质量监督体系式关系着建筑施工企业发展的命脉,做好现场施工管理是基建工作中的重中之重。文章分析探讨了加强基建工程现场施工管理的几个环节。 随着现代科学技术的发展,桩的种类和桩基形式、施工工艺和设备以及桩基理论和设计方法,都有了很大的演进。桩基已成为在土质不良地区修建各种建筑物特别是高层建筑,重型厂房和具有特殊要求的构筑物所广泛采用的基础形式。 ?针对当前工程项目全过程中造价成本控制不力的现状,本论文也将分析讨论了在全过程中实施全过程造价控制与管理的措施,对于提高工程全过程造价管理控制水平具有一定的意义。 工程技术资料的整理和归档是建筑工程必不可少的工作之一,为了能更好地做好建筑工程技术资料整理工作,就建筑工程技术资料的重要性及做好资料整理要注意的几个方面进行简单的分析。 ?本文将在以上几个方面展开相关的论述。 关键词: 建筑工程技术现场施工管理方法深基坑土钉支护桩基混 凝土造价控制造价管理资料

建筑学本科毕业设计任务书

湖南城市学院建筑学本科(函授) 毕业设计任务书 一、设计题目:青少年活动中心 二、任务要求 1.建设地点:中国南方某城市:夏季主导风向为东南风,冬季主导风向为西北风; 2.用地概况:基地位于南方某市新开发区内。基地内地形平整,基地东北侧为规划中的体育运动学校用地,东南为市新修的博物馆。南面为市体育中心,北面是人民公园,西面为新建的居住小区(见附图)。拟建的青少年活动中心将为该市提供功能齐全、设施优良、环境舒适的现代化青少年活动基地,其建成后将与体育中心、博物馆一起成为城市文体活动的中心。 3.规划要求 (1)用地的东南西北四面建筑控制线由用地红线后退5m。建筑物不得突出建筑控制线。 (2)建筑层数不超过五层,总高度低于24米。建筑占地率小于40%,容积率小于0.66,绿化率大于30%,地面停车位60个。

四、设计要求 1.总建筑面积12000m2;(允许有10%增减) 2.功能空间及使用面积分配如下表:

3.室外场地设计中应设置主入口礼仪广场、室外集中活动场地、室外网球场一个,室外篮球场、排球场各两个; 4.总平面中综合解决好功能分区、出入口、停车位、道路、绿化、日照、卫生、消防等问题。 5.紧密结合基地环境,处理好体育中心与活动中心的关系,尤其是在建筑风格与建筑体量方面的呼应;处理好室外活动场地与室外环境。 6.熟悉青少年活动中心的设计要点,基本做到功能布局合理、交通流线通畅、室内外空间组织有序,同时符合青少年活动的行为特征。 7.要考虑并体现青少年文体建筑积极向上、活泼灵动的现代建筑造型特点,并结合南方已有的建筑元素,加以整合与利用。 8.考虑无障碍设施,以符合以人为本的设计理念。 五、图纸要求 1.总平面布置(1:500) (1)标明道路、绿化、小品、室外入口广场、网球场、篮球场、排球场、停车位和出入口的位置; (2)标明技术经济指标:用地面积、建筑密度、容积率和绿化面积。 2.单体设计 (1)各层平面图(1:200),标注轴线及开间尺寸,画出墙体、柱、楼梯、门窗洞口及门的开启方向,注写房间名称,一层平面图应有环境设计,并标注剖切符;(2)立面图图四个(1:200); (3)剖面图1-2个(1:200),剖切位置应选择在楼梯间和能最大限度地表现建筑内部空间的位置。注明各层楼地面标高、屋面坡度、关键尺寸; (4)建筑外观效果图和必要的分析图 3.毕业设计论文(包括建筑设计构思、说明、经济技术指标以及对方案设计的理解等内容,字数不少于3000字)。 六、其他 1.建筑面积一律按轴线尺寸计算; 2.图纸、文字一律采用计算机绘制。

房屋建筑学毕业论文选题

房屋建筑学毕业论文选题

毕业论文(设计) 题目 学院学院 专业 学生姓名 学号年级级指导教师 教务处制表 二〇一三年三月二十日

房屋建筑学毕业论文选题 本团队专业从事论文写作与论文发表服务,擅长案例分析、仿真编程、数据统计、图表绘制以及相关理论分析等。 房屋建筑学毕业论文选题: 山区乡村建筑洪水冲击作用可视化研究 房屋质量保险制度下质量检查机构运行机制研究 山区乡村建筑洪水作用荷载试验研究 木构架砖围护墙房屋的拟静力试验研究 基于玻化微珠保温混凝土既有砌体房屋抗震加固与节能改造一体化研究 夯土房屋纵横墙交接处裂缝成因及其预控措施研究 既有建筑顶部钢结构加层的结构设计与抗震性能分析 广东沿海典型低矮建筑调研与风荷载特性的试验研究 基于建筑和结构安全统一的废旧集装箱改造房构造的研究 从建筑到村落形态 城市房屋拆迁补偿制度研究 关于《危险房屋鉴定标准》的应用研究 现有小高层钢筋混凝土房屋的抗震鉴定与加固 现代木结构建筑之墙体构造研究 云南传统民居建筑抗震加固方法的研究 澜沧江中下游流域传统聚落研究初探村落人居环境与建筑朝向生态的可持

续发展 沈阳周边村镇砌体结构学校建筑抗震性能研究 湖南省村镇砖砌体房屋抗震施工方法及质量控制研究 多层砌体房屋的抗震鉴定研究 低层建筑表面风荷载数值模拟研究 大庆地区房屋结露发霉治理技术研究 汶川地震中村镇建筑的震害分析及抗震减灾措施研究 夯土墙承重房屋的局部受压性能研究 太阳能技术在建筑上的应用研究 汶川地震房屋震害分析及抗震鉴定方法的研究 西安老城区宗教建筑修复与保护研究 抗震设防建筑的易损性及震害指数研究 砌块建筑裂缝成因及处理技术研究 混凝土砌块建筑裂缝及渗漏处理技术研究 低层砌体住宅房屋简化设计及施工质量控制 国内外房屋建筑物管理制度的比较和借鉴 红外热像技术在建筑结构节能中的应用研究 情感·建筑·城 高速公路服务区建筑设计研究 多层砌体结构房屋震后鉴定及加固研究 传统木结构建筑抗震性能试验研究 多层砖混结构房屋抗震构造措施研究 TTU标模及平顶罩棚类低矮建筑的风洞试验研究 摩擦滑移减震技术在村镇砌体房屋结构中的应用可行性研究及减震效果分析 建筑外墙饰面检测维修优化分析 山区乡村建筑洪水冲击破坏数值模拟研究 住宅建筑计量供热自力式差压控制阀及热计费问题的研究 云南农村民居新建房屋夯土墙竹筋加固的试验研究

交通工程毕业论文

交通工程毕业论文 Revised by Chen Zhen in 2021

继续教育学院 毕业论文 题目:江西吉安地区某二级公路的设计 学生姓名:袁隆寒 考籍号: 班级:海南自考 专业:交通土建 指导老师: 2014年6月

(江西吉安地区某二级公路的设计)学生姓名:袁隆寒 考籍号: 站点:指导教师: 完成日期:

摘要 本设计主要完成了江西吉安地区某二级公路的设计。根据给定的材料,以及结合当地的自然和经济情况,进行了纸上选线等设计。该设计主要以路线为主,并兼顾了其他方面。路线部分首先根据设计交通量确定了公路的等级,公路等级确定主要技术标准并进行路线平面设计,对路线进行了局部比选;考虑填挖平衡及最小填土高度进行了纵断面设计;对局部进行了横断面设计,绘出路基横断面图,对路基进行加宽和超高计算,编制路基设计表,进行土石方计算及调配;为保证路基处于干燥的稳定状态,对路基路面进行了排水设施设计;对涵洞尺寸标高进行了初步拟定,并对路基工程进行了局部土石方分项预算。 关键词:路线路面路基防护分项预算

Abstract The main Summary of this design had completed a two highway design in a certain area of Ji'an in Jiangxi. The main task of the design is primarily of routes, and to take into account the other aspects. The line design is determined according to the Highway grading standards to have the main technical and graphic design for the road on the route having comparing with the local. Considering filling dug balance and minimum height of filling, the profile design is drawn. Make a design for the cross-sectional, then draw cross-sectional map. After have calculation of roadbed for widening and elevation, drafting the questionnaire design, earthwork calculations and deployment; To ensure road embankment in the stability of dry, it make road drainage facilities design; Elevation culvert size of the initial formulation, and have embankment works at the project budget. Keywords: Route;Pavement;Subgrade;Protection;Budget breakdown

建筑工程毕业设计论文模板

黑龙江林业职业技术学院 建筑工程技术毕业设计(论文)规范要求(试行) 一、一般格式和顺序 1、封面:(格式见封面范本) (1)题目:应能高度概括整个论文最重要的内容,具体、切题、不能太笼统,但要引人注目;题名力求简短,严格控制在25字以内。 (2)专业方向:以中华人民共和国教育部高等教育司批准的专业为准。 (3)指导教师:指导教师的署名一律以实际指导的教师为准,最多只能填写两名指导教师。 2、中文摘要:论文第一页为中文摘要,150-200字左右。内容应包括课题设计意义、完成的主要工作、重要结 论及其理论和技术水平,要突出本论文的创造性成果,语言力求精炼。 3、关键词:为了便于文献检索,要求作者从正文或标题中挑选出3-5个能表达其主要内容的词语在本页下方另 起一行作为论文的关键词。(格式见摘要范本) 4、目录:应是论文的提纲,也是论文组成部分的小标题。(格式见目录范本) 5、引言:在论文正文前,作者应对本项研究的国内外已有的文献进行综述,包括研究历史、现状、动态和发展 趋势,并说明设计的背景、理论依据、预期结果及其在相关领域的地位、实用价值。(500字左右)。 6、正文:是毕业设计(论文)的主体。要求作者在本部分真实全面地反映其工作量和工作水平,创造性成果或 新的研究成果。写作内容可因研究课题性质而不同,一般可包括:研究地区自然概况(包括试验地的自然状况(行政隶属关系、经纬度、气候条件、土壤条件、植被条件等)和社会经济状况等,研究方法(包括试验地设置、样地调查、样品采集方法和数据处理等)、结果分析。力求做到主题明确,数据可靠,内容充实,论据充分,论证严密,层次分明,脉络清晰。 7、结论和讨论:要求作者根据设计(论文)过程中所获得的全部数据和材料,经过科学分析、准确判断和合理 归纳等逻辑处理,得出正确的学术观点和新颖的见解,结论表述必须准确、精炼、缜密和完整,使人能够从结论中全面了解论文的意义、目的、内容和主要研究结果。要认真阐述自己工作的创造性在本领域中的地位、作用和意义,以及本设计(论文)存在的不足及其完善的可能性。 8、参考文献:要求列出作者直接阅读过、在正文中曾被引用过、正式发表的文献资料,以示对文献作者的尊重。 参考文献的写法见论文书写的有关部分。参考文献一律放在论文结论后,不得放在各部分之后。 9、致谢:致谢对象限于在毕业设计(论文)过程中对自己论文的完成有较重要帮助的个人和集体等。(限200 字以内) 10、附录:可以包括正文内不便列出的冗长的公式推导;以备他人阅读方便所需的辅助性数学工具或表格;重 复性数据图表;计算程序及说明等。 11、毕业设计(论文)评语:该部分由毕业设计(论文)指导教师和论文评阅人亲笔填写。(格式见评语范本) 二、论文的书写 1、语言表述 (1)设计(论文)应立论正确,层次分明,数据可靠,文字简练,说明透彻,推理严谨,避免使用非学术性和不规范的词语。 (2)论文中如出现一个不为学术界熟悉的、非通用性的新概念、新名词或新术语,需清楚地加以解释和说明。 2、层次和标题 (1)层次要清楚:标题要重点突出,简明扼要。

建筑施工组织设计毕业论文

建筑施工组织设计毕业论文 第一章编制依据说明 编制依据: 1.本工程施工图纸及图纸答疑 2.现行的国家有关质量验收规及相关政策法规 4.我公司对工程施工现场的实地考察和公司承接的相关类似工程的实际管理和施工技术经验 5.我公司现行的有关技术规定和规程 (二)编制原则 (1)施工组织设计的基本宗旨是按照建筑工程建设的基本规律,施工工艺规律和经营管理规律,制定科学合理的组织方案,施工方案,合理安排施工顺序和进度计划,有效利用施工场地,优化配置和节约使用人力、物力、资金、技术等生产要素,协调各方面的工作,施工有计划、有节奏,能够保证质量、进度、安全、文明,取得良好的经营效益,社会效益和环境效益。 (2)结合我公司施工技术力量,机械设备等综合条件以及工程特点和施工条件,编制具有全面性、可行性、针对性、先进性。本公司现有施工技术装备、劳动力、资源及在近几年承建和在建的同类工程中积累的较为成熟的施工经验。

第二章工程概况 一、总说明 1.工程名称:大润发大型商场 2.工程地点:位于宿迁市幸福南路13号。 3.建设单位:宏大建设 4.设计单位:建筑设计 5.建筑面积:3095.04 6.结构层次:一至六楼全为框架 7.管理目标 ①质量目标:确保合格,力争优良工程 ②安全目标:杜绝重大人身伤亡和机电事故 二、一般说明 本工程位于位于宿迁市幸福南路13号。 本工程占地总面积515.84,建筑面积3095.04。建筑耐火耐火等级2级,屋面防水等级3级。建筑层数六层,耐久年限50年,抗震设防烈度6度。 结构为一至六楼全为框架框架,。 砼等级:垫层为C10素砼,基础、阳台、雨篷、构架、架空层砼为C30,B、C区基础顶面至标高3.5米柱、梁、板、墙为C30。卫生间为C25,构造柱、圈梁等未注明的现浇构件为C20。 墙体工程 1.一层框架部分填充墙为加气混凝土砌块,±0.00标高以上其他

建筑专业本科毕业论文(2)

中央广播电视大学开放教育会计专业本科毕业论文 浅谈企业应收账款管理 姓名 学号 工作单位 所在分校 指导教师 XX广播电视大学制 二O一一年十一月

写作提纲 一、加强应收账款管理的意义 二、当前应收账款管理中存在的问题 三、加强应收账款管理的具体措施

内容提要 应收账款是企业因销售商品、提供劳务而形成的债权,大量呆帐、坏帐的产生,给企业带来了极大的经营风险,主要包括以下方面:1、占用企业生产经营资金,降低企业资金周转速度。2、增加企业的现金流出。3、形成坏账损失,影响企业经营业绩。 应收账款产生的各种风险不可低估,但应收账款在每个企业普遍存在,产生的原因大致可以归纳为以下几点:1、来源于激烈的市场竞争。2、企业内部管理不力。3、忽视对客户信用的调查和管理。4、企业风险意识不强。5、运用法律手段解决债务纠纷的意识不强。 企业要适应经济全球化的发展趋势,认为可以从以下方面加强对企业应收账款管理,减少坏账损失的发生:一、加强销售合同的管理。二、划分赊销制度,审批权限,分别确定责任人的权限X围。三、建立合理的考核制度和健全的内部约束机制。四、建立严格的应收账款内部控制。五、制定切实可行的信用政策,选择对企业有利的结算方式。六、积极运用法律手段加大追索债务的力度要求企业业务人员,强化法律意识,充分运用法律手段清理欠款,以维护企业合法权益。

浅谈企业应收账款管理 应收账款是企业因销售商品、提供劳务而形成的债权,具有资产的某些属性,其一,在应收账款的持有时间内,会丧失部分时间价值;其二,随着时间的推移,它还可能因为债务人的破产等原因而无法收回,形成坏账,其影响程度取决于应收账款的规模,规模越大,负面影响越大;同时也取决于应收账款账龄的长短,账龄越长,坏帐损失产生的风险越大。大量呆帐、坏帐的产生,给企业带来了极大的经营风险,主要包括以下方面: 1、占用企业生产经营资金,降低企业资金周转速度。应收账款代表企业的债权,未实现现金的流入,属于应收而未收的资产,应收账款的不断增加,使企业资金的周转速度减慢,使大量的流动资金沉淀在非生产环节,致使企业的生产经营资金短缺,影响了企业正常的生产经营; 2、增加企业的现金流出。(1)应收账款的发生意味着企业销售收入的成立。流转税是以销售收入为计算依据,按期以现金方式缴纳。(2)应收账款使企业利润增加,企业盈利后需缴纳企业所得税。(3)应收账款的管理成本(即信用调查费用、信用收集费用、账簿记录费用、收账费用等)会增加企业的现金流出; 3、形成坏账损失,影响企业经营业绩。坏账是企业无法收回或收回的可能性极小的应收账款。由于发生坏账而产生的损失,称为坏账损失。企业对发生的坏账依法处理后,作为企业的一项经营发生的管理费用会冲减企业利润。 虽然应收账款的存在将产生种种潜在的财务及经营风险,但随着我国市场经济体制的逐步建立和企业间的激烈竞争,应收账款作为企业的一种商业信用和促销手段,仍被企业广泛采用。当前,我国绝大多数企业都面临“销售难、收款更难”的双重困境。一方面,市场竞争日益激烈,为争取客户订单,企业提供几近苛刻的优惠条件,利润越来越低;另一方面,客户拖欠账款,销售人员催收不力,产生大量呆帐、坏帐,使本已微薄的利润更被严重侵蚀,给企业的发展带来了极大的风险,应收账款产生的各种风险不可低估,但应收账款在每个企业普遍存在,产生的原因大致可以归纳为以下几点: 1、来源于激烈的市场竞争。如在家电行业,由于产品更新换代非常快,为提高市场占有率,生产厂家除发动“价格战”争夺顾客以外,还通过降低赊销信用的

相关文档
相关文档 最新文档